526 W 148TH ST 90248
Certificate Information: 526 W 148TH ST 90248
- Application / Permit
- 19014-20000-04992
- Plan Check / Job No.
- B19VN15408
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (5'-10" X 12') ADDITION AT REAR OF (E) SFD FOR (N) BATHROOM AND TO ENLARGE KITCHEN. ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofO Issued on 2/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2019 | RAPHAEL ROSAS |
| Corrections Issued | 9/11/2019 | RAPHAEL ROSAS |
| Plan Check Approved | 9/12/2019 | PINANK PATEL |
| Issued | 8/9/2021 | APPLICANT |
| Building Plans Picked Up | 8/10/2021 | APPLICANT |
| CofO in Progress | 2/18/2022 | EUGENE CASSIDY |
| Permit Finaled | 2/24/2022 | DEROLD HAUFF |
| CofO Issued | 2/24/2022 | DEROLD HAUFF |
| Permit Finaled | 2/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 9/11/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/11/2019 | GUILLERMO PETRA |
| Hold | Cleared | 9/7/2021 | JASON SHEETS |
| Hold | Cleared | 9/7/2021 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/1/2021 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 11/1/2021 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 11/1/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/9/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 11/9/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/15/2021 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 11/15/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| MERV13>=Rough | 11/15/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| METHANE-Rough | 11/15/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Interior/Exterior Lathing | 12/2/2021 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 12/6/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/6/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 12/6/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 12/6/2021 | Partial Approval | EUGENE CASSIDY |
| MERV13>=Rough | 12/6/2021 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 12/6/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 12/6/2021 | Approved | EUGENE CASSIDY |
| Shower Pan | 12/6/2021 | Approved | EUGENE CASSIDY |
| Insulation | 12/7/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 12/9/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/21/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/21/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/21/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/21/2022 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 1/21/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/21/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 1/21/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/2/2022 | Corrections Issued | JOHN KLARIN |
| Smoke Detectors | 2/2/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 2/4/2022 | Approved | AMY COLIN |
| Final | 2/17/2022 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 2/17/2022 | Approved | EUGENE CASSIDY |