4824 N VINCENT AVE 90041
Certificate Information: 4824 N VINCENT AVE 90041
- Application / Permit
- 19014-20000-04989
- Plan Check / Job No.
- B19VN15402
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (17'-10"x 23'-6") IRR SHAPE ACCESSORY DWELLING UNIT. PER AB 494 AND SB 229 TO AND CONVERT (E) (19'-9"x 18'-9") CARPORT INTO TWO CAR GARAGE AND ATT (E) (9'-1"x 11'-2") STORAGE. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/15/2020
- Issuing Office
- Current Status
- CofO Issued on 4/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | TROY DEGUZMAN |
| Corrections Issued | 10/8/2019 | TROY DEGUZMAN |
| Quality Review Completed | 10/9/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 10/28/2019 | APPLICANT |
| Green Plans Picked Up | 10/28/2019 | APPLICANT |
| Applicant returned to address corrections | 2/27/2020 | TROY DEGUZMAN |
| Plan Check Approved | 7/15/2020 | TROY DEGUZMAN |
| Issued | 7/15/2020 | APPLICANT |
| CofO in Progress | 4/21/2022 | CRAIG VAUGHAN |
| Permit Finaled | 4/25/2022 | DEROLD HAUFF |
| CofO Issued | 4/25/2022 | DEROLD HAUFF |
| Permit Finaled | 4/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 1/3/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 1/3/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 1/31/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/31/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2020 | JOHN LIN |
| Sewer availability | Cleared | 2/3/2020 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 2/27/2020 | MANUEL TEJADA |
Contact Information
| Architect | Sturgill,, Ben Curtis; Lic. No.: C23174 | 314 E BROADWAY # E GLENDALE, CA 91205 |
| Contractor | Owner-Builder | , |
| Engineer | Simonian,, Ara; Lic. No.: C37208 | 314 E BROADWAY STE A GLENDALE, CA 91205 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/21/2020 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/14/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/15/2020 | Approved | CRAIG VAUGHAN |
| Special/Order Compliance | 11/4/2020 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 11/17/2020 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/24/2020 | No Access for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/24/2020 | No Access for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/23/2020 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2020 | Partial Approval | SCOTT FINNILA |
| Gas Test | 12/23/2020 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 12/23/2020 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 12/23/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 1/13/2021 | Corrections Issued | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/13/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/13/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 1/13/2021 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/20/2021 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 1/20/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/20/2021 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 1/20/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 1/20/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 1/26/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 1/26/2021 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 2/3/2021 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 3/26/2021 | Approved | CRAIG VAUGHAN |
| Final | 3/26/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/26/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 3/26/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 3/26/2021 | Approved | CRAIG VAUGHAN |
| Final | 4/26/2021 | Partial Approval | CRAIG VAUGHAN |
| Gas Test | 4/26/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 4/26/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Final | 5/6/2021 | OK to Issue CofO | CRAIG VAUGHAN |