1412 N FLORESTA PL 90272

Certificate Information: 1412 N FLORESTA PL 90272

Application / Permit
19014-20000-04987
Plan Check / Job No.
B19VN15399
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 33'3" X 15'7" IRREGULAR 1ST FLOOR ADDITION TO (E) SFD TO CREATE NEW DINING ROOM AND NEW LIVING ROOM , NEW 23'1" X 24'9" 1ST FLOOR ADDITION TO (E) SFD TO ENLARGE THE LIVING ROOM , ENLARGE ENTRY FOYER, NEW BAY WINDOW AT FAMILY ROOM , NEW 45'6" X 24'11" 2ND FLOOR ADDITION TO (E) SFD TO CREATE MASTER BEDROOM , MASTER BATHROOM , MASTER W.I.C. AND (2) BALCONIES , NEW 83 ' X 47' IRREGULAR SHAPED ROOFTOP DECK , RE-FRAME ROOF , NFPA-13D FIRE SPRINKLERS REQURED, ALL WORK ENGINEERING
Permit Issued
Issued on 9/29/2020
Issuing Office
Valley
Current Status
Issued on 9/29/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 RARES BODEA
Green Plans Picked Up 10/8/2019 APPLICANT
Corrections Issued 10/10/2019 RARES BODEA
Quality Review Completed 10/15/2019 GUANG MIN TUNG
Building Plans Picked Up 10/16/2019 APPLICANT
Applicant returned to address corrections 11/15/2019 RARES BODEA
Applicant returned to address corrections 11/25/2019 RARES BODEA
Applicant returned to address corrections 1/23/2020 RARES BODEA
Applicant returned to address corrections 8/12/2020 RARES BODEA
Plan Check Approved 8/17/2020 RARES BODEA
Issued 9/29/2020 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/31/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 10/31/2019 ELENA LOPEZ
Sewer availability Cleared 10/31/2019 ELENA LOPEZ
BHO/Hillside ordinance Cleared 11/1/2019 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 11/1/2019 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 11/1/2019 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 11/1/2019 MAHELET GEBEYHU
Miscellaneous Cleared 11/5/2019 DAISY BENICIA
Miscellaneous Cleared 11/5/2019 DAISY BENICIA
Miscellaneous Cleared 11/5/2019 DAISY BENICIA
Hydrant and Access approval Cleared 11/26/2019 GEORGE SUCHAND
Green Code Cleared 11/27/2019 MICHAEL AYERS
Coastal Zone Cleared 1/13/2020 HERMINIGILDO AGUSTIN
ZI Cleared 1/13/2020 HERMINIGILDO AGUSTIN
Distance to fire station Cleared 1/22/2020 GEORGE SUCHAND
GPI Written Notices Cleared 1/23/2020 RARES BODEA
Grading Pre-Inspection Cleared 1/23/2020 RARES BODEA
Low Impact Development Cleared 6/16/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 8/5/2020 DINAH GARIN

Contact Information

Contractor Home Improvement Services Inc; Lic. No.: 903938-B 18375 VENTURA BLVD UNIT 416      TARZANA, CA 91356
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Korganyan,, Karen; Lic. No.: L8510 5642 ETIWANDA AVE 9      TARZANA, CA 91356

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/24/2020 Partial Inspection JOHN MATTILLO
Footing/Foundation/Slab 12/18/2020 Approved JOHN MATTILLO
Structural Steel Frame 1/19/2021 Partial Approval JOHN MATTILLO
Wood Frame 1/19/2021 Partial Approval JOHN MATTILLO
BUILDING-Rough-Frame 2/18/2021 Not Ready for Inspection MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 2/18/2021 Partial Approval MARIAN PODPORA
Green Building Rough 2/18/2021 Not Ready for Inspection MARIAN PODPORA
BUILDING-Rough-Frame 5/10/2021 Corrections Issued JOHN MATTILLO
ELECTRICAL-Rough 5/10/2021 Corrections Issued JOHN MATTILLO
Green Building Rough 5/10/2021 Corrections Issued JOHN MATTILLO
HVAC-Rough 5/10/2021 Corrections Issued JOHN MATTILLO
PLUMBING-Rough 5/10/2021 Corrections Issued JOHN MATTILLO
ELECTRICAL-Rough 5/12/2021 Approved JOHN MATTILLO
HVAC-Rough 5/12/2021 Partial Approval JOHN MATTILLO
PLUMBING-Rough 5/12/2021 Approved JOHN MATTILLO
Wood Frame 5/12/2021 Partial Approval JOHN MATTILLO
Insulation 8/27/2021 Approved JOHN MATTILLO
Interior/Exterior Lathing 8/27/2021 Partial Approval JOHN MATTILLO
Interior/Exterior Lathing 10/1/2021 Partial Approval MARIAN PODPORA
Shower Pan 10/1/2021 Approved MARIAN PODPORA
Drywall Nailing 11/19/2021 Not Ready for Inspection MARIAN PODPORA
Green Building Rough 11/19/2021 Approved MARIAN PODPORA
Drywall Nailing 12/28/2021 Corrections Issued MARIAN PODPORA
ELECTRICAL-Rough 1/24/2022 Corrections Issued MARIAN PODPORA
Drywall Nailing 2/1/2022 Approved MARIAN PODPORA
ELECTRICAL-Rough 2/1/2022 Approved MARIAN PODPORA
HVAC-Final 2/1/2022 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Final 2/1/2022 Not Ready for Inspection MARIAN PODPORA
BUILDING-Rough-Frame 3/18/2024 Approved JOHN MATTILLO
Final 3/18/2024 Corrections Issued JOHN MATTILLO
Green Building Final 3/18/2024 Approved JOHN MATTILLO
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved JOHN MATTILLO
Smoke Detectors 3/18/2024 Approved JOHN MATTILLO