5315 E RANGE VIEW AVE 90042
Certificate Information: 5315 E RANGE VIEW AVE 90042
- Application / Permit
- 19014-20000-04979
- Plan Check / Job No.
- B19VN15365
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- 4'8"X19'3" 1ST FLOOR GARAGE ADDITION; 21'0"X10'6" IRREGULAR SHAPED 1ST FLOOR REC ROOM ADDITION WITH 4'8"X7'0" COVERED PATIO; 21'0"X29'9" ADU ADDITION ON 2ND FLOOR OF (E) GARAGE PER AB 494 AND SB 229. (E) GARAGE TO REMAIN
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | MARVEL DELACRUZ |
| Corrections Issued | 10/9/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 10/10/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/15/2019 | APPLICANT |
| Green Plans Picked Up | 10/15/2019 | APPLICANT |
| Applicant returned to address corrections | 3/4/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 3/13/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 3/16/2020 | MARVEL DELACRUZ |
| Issued | 3/18/2020 | LADBS |
| CofO in Progress | 3/4/2022 | CRAIG VAUGHAN |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
| Permit Finaled | 3/11/2022 | DEROLD HAUFF |
| CofO Issued | 3/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/29/2019 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 12/24/2019 | MICHAEL AYERS |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2020 | CELINA MORENO |
| Low Impact Development | Cleared | 3/16/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/16/2020 | CELINA MORENO |
| Sewer availability | Cleared | 3/16/2020 | CELINA MORENO |
Contact Information
| Contractor | J M A General Contractor; Lic. No.: 893018-B | 5817 MCDONIE AVENUE WOODLAND HILLS, CA 91367 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/3/2020 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 6/12/2020 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | Partial Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/1/2020 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/21/2020 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/31/2020 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 8/31/2020 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/31/2020 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/11/2020 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2020 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 9/11/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 9/11/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/22/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/22/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/29/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/29/2020 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/5/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 10/5/2020 | Approved | CRAIG VAUGHAN |
| Insulation | 10/14/2020 | Approved | COREY HUPP |
| Shower Pan | 10/14/2020 | Approved | COREY HUPP |
| Drywall Nailing | 10/20/2020 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 10/20/2020 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/24/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 5/3/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 5/3/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 5/3/2021 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 5/3/2021 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/25/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/25/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 1/18/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 1/18/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/18/2022 | SGSOV Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/10/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 2/10/2022 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 2/10/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 2/10/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/3/2022 | Approved | CRAIG VAUGHAN |
| Final | 3/3/2022 | OK to Issue CofO | CRAIG VAUGHAN |