8029 S REGIS WAY 90045
Certificate Information: 8029 S REGIS WAY 90045
- Application / Permit
- 19014-20000-04961
- Plan Check / Job No.
- B19VN15303
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 2'4" X 8'9" AND 2' X 7'8" PORTION OF (E) 1ST FLOOR , NEW 2'10" X 10'6" 1ST FLOOR ADDITION TO (E) SFD TO ENLARGE THE DINING ROOM , NEW 2' X 2'3-1/2" ADDITION TO (E) SFD TO ENLARGE CLOSET, NEW 56'5" X 26'6" SECOND FLOOR ADDITION TO CREATE (3) BEDROOMS , (2) BATHROOMS , W.I.C. , MAJOR REMODEL TO (E) SFD TO RELOCATE KITCHEN, LAUNDRY ROOM BATHROOM , REMOVE (3) BEDROOMS, REMODEL KITCHEN , LIVING ROOM , CONVERT BEDROOM TO FAMILY ROOM , ADD 4' X 15' 1ST FLOOR OPEN TRELLIS AND 14' X 12'1" SECOND FLOOR OPEN TRELLIS , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | RARES BODEA |
| Corrections Issued | 9/21/2019 | RARES BODEA |
| Quality Review Completed | 9/24/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 9/27/2019 | APPLICANT |
| Green Plans Picked Up | 9/27/2019 | APPLICANT |
| Plan Check Approved | 10/31/2019 | RARES BODEA |
| Issued | 11/2/2021 | APPLICANT |
| CofO in Progress | 9/29/2023 | BOBBY KEY |
| Permit Finaled | 10/4/2023 | DANIEL ORRANTE |
| CofO Issued | 10/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2019 | JOHN LIN |
| Sewer availability | Cleared | 10/15/2019 | JOHN LIN |
| ZA Case | Cleared | 10/15/2019 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 10/18/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/18/2019 | THOMAS LANG |
| Green Code | Cleared | 10/22/2019 | AARON COSTA |
Contact Information
| Contractor | Pagan Robert M Construction Company; Lic. No.: 509594-B | 8125 LOYOLA BLVD LOS ANGELES, CA 90045 |
| Engineer | Avila,, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/8/2022 | Corrections Issued | BOBBY KEY |
| Deputy Drilled-In Anchors | 3/8/2022 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 3/8/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 3/8/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/11/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 3/15/2022 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Partial Approval | BOBBY KEY |
| Deputy Wood Construction | 5/5/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 9/9/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 9/9/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 9/26/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 9/26/2022 | Approved | BOBBY KEY |
| Green Building Rough | 9/26/2022 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 9/26/2022 | Conditional Approval | BOBBY KEY |
| Insulation | 10/18/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 10/25/2022 | Approved | BOBBY KEY |
| Final | 10/25/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 10/25/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 10/25/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | BOBBY KEY |
| Sewer | 10/26/2022 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 1/30/2023 | Partial Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 2/3/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/8/2023 | Partial Approval | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/8/2023 | SGSOV Approved | BOBBY KEY |
| Sewer | 4/4/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 5/25/2023 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 5/25/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 5/30/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 5/30/2023 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 5/30/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/1/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 6/1/2023 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 6/5/2023 | Approved | BOBBY KEY |
| Final | 6/5/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 6/5/2023 | Approved | BOBBY KEY |
| Final | 9/29/2023 | OK to Issue CofO | BOBBY KEY |
| Green Building Final | 9/29/2023 | Approved | BOBBY KEY |
| Service/Power Release | 9/29/2023 | Approved | BOBBY KEY |