10956 W TENNESSEE AVE 90064
Certificate Information: 10956 W TENNESSEE AVE 90064
- Application / Permit
- 19014-20000-04947
- Plan Check / Job No.
- B19VN15259
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (23'-5" X 31'-8") IRREGULAR SHAPED 2-STORY ADDITION TO (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/5/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | RAPHAEL ROSAS |
| Corrections Issued | 9/21/2019 | RAPHAEL ROSAS |
| Quality Review Completed | 9/24/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 9/25/2019 | APPLICANT |
| Green Plans Picked Up | 9/25/2019 | APPLICANT |
| Plan Check Approved | 10/24/2019 | RAPHAEL ROSAS |
| Issued | 11/5/2019 | LADBS |
| CofO in Progress | 6/9/2020 | KENNETH NAGLE |
| Permit Finaled | 6/9/2020 | VINCENT COTTON |
| CofO Issued | 6/9/2020 | VINCENT COTTON |
| Permit Finaled | 6/9/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2019 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 10/11/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 10/11/2019 | JEANETTE VONG |
| Green Code | Cleared | 10/15/2019 | AARON COSTA |
| Sewer availability | Cleared | 10/15/2019 | GUILLERMO PETRA |
| GPI Written Notices | Cleared | 10/24/2019 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 10/24/2019 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/21/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 11/21/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Excavation/Setback/Form/Re-Bar | 11/25/2019 | Approved | KEVIN BEAULIEU |
| Rough-Elec/Plmb/HVAC | 12/18/2019 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 12/18/2019 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2020 | Partial Approval | KEVIN BEAULIEU |
| Wood Frame | 1/6/2020 | Partial Approval | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2020 | Partial Approval | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2020 | Partial Approval | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 1/22/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2020 | Conditional Approval | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 2/11/2020 | Conditional Approval | KEVIN BEAULIEU |
| ELECTRICAL-Rough | 2/11/2020 | Approved | KEVIN BEAULIEU |
| Green Building Rough | 2/11/2020 | Approved | KEVIN BEAULIEU |
| HVAC-Rough | 2/11/2020 | Approved | KEVIN BEAULIEU |
| PLUMBING-Rough | 2/11/2020 | Approved | KEVIN BEAULIEU |
| Wood Frame | 2/11/2020 | Conditional Approval | KEVIN BEAULIEU |
| Wood Frame | 2/13/2020 | Approved | KEVIN BEAULIEU |
| Insulation | 2/14/2020 | Approved | KEVIN BEAULIEU |
| Drywall Nailing | 2/18/2020 | Approved | KEVIN BEAULIEU |
| Shower Pan | 2/26/2020 | Approved | KEVIN BEAULIEU |
| Interior/Exterior Lathing | 3/2/2020 | Approved | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 4/13/2020 | Conditional Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 4/13/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Final | 4/13/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/13/2020 | Approved | ANTHONY MCDOWALL |
| Green Building Final | 4/13/2020 | Conditional Approval | ANTHONY MCDOWALL |
| HVAC-Final | 4/13/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Final | 4/13/2020 | Corrections Issued | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 4/13/2020 | SGSOV Not Ready | ANTHONY MCDOWALL |
| Smoke Detectors | 4/13/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 4/16/2020 | Approved | ANTHONY MCDOWALL |
| HVAC-Final | 4/16/2020 | Conditional Approval | ANTHONY MCDOWALL |
| PLUMBING-Final | 4/16/2020 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 5/18/2020 | Approved | EVAN COOPER |
| Final | 5/18/2020 | Conditional Approval | EVAN COOPER |
| Green Building Final | 5/18/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/18/2020 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/18/2020 | Approved | EVAN COOPER |