2237 W AARON ST 90026

Certificate Information: 2237 W AARON ST 90026

Application / Permit
19014-20000-04932
Plan Check / Job No.
B19VN15217
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Reframe 2/3 roof, replace 7 windows and 18 doors, remodel kitchen, convert upper level bedroom to den and 12.5' x 37' portion of lower level garage area to bedroom and utility room, create 2 new bathrooms; remove side balcony and add 12' x 30.75' patio cover with roof deck. All works are per design
Permit Issued
Issued on 9/24/2019
Issuing Office
San Pedro
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2019 APPLICANT
Assigned to Plan Check Engineer 9/9/2019 ALDOUS CHIC
Corrections Issued 9/9/2019 ALDOUS CHIC
Plan Check Approved 9/19/2019 ANGELICA MARTINEZ
Issued 9/24/2019 LADBS
CofO in Progress 10/25/2024 HAMIK HARTOUNIAN
CofO Issued 11/1/2024 DEROLD HAUFF
Permit Finaled 11/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/11/2019 LEE GUILBEAUX
Sewer availability Cleared 9/11/2019 LEE GUILBEAUX
Low Impact Development Cleared 9/19/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/19/2019 ADRIAN CASTRO

Contact Information

Contractor G A Design Build; Lic. No.: 941130-B 8449 EVEREST ST      DOWNEY, CA 90242
Engineer Lee,, Richard C C; Lic. No.: S1371 19558 GAULT ST      RESEDA, CA 91335

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2019 No Access for Inspection DAVID CHAN
PLUMBING-Rough 11/1/2019 Partial Approval DAVID CHAN
ELECTRICAL-Rough 11/20/2019 Not Ready for Inspection AJA COLLAY
Floor/Roof Diaphrgm/Shear Wall 11/20/2019 Corrections Issued AJA COLLAY
PLUMBING-Rough 11/20/2019 Not Ready for Inspection AJA COLLAY
ELECTRICAL-Rough 11/23/2019 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/23/2019 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 11/23/2019 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 11/23/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/3/2020 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/10/2020 Partial Approval BRAD BESCOS
PLUMBING-Rough 2/10/2020 Corrections Issued BRAD BESCOS
Insulation 2/14/2020 Conditional Approval AJA COLLAY
Interior/Exterior Lathing 2/14/2020 Approved AJA COLLAY
Shower Pan 2/14/2020 Approved AJA COLLAY
Drywall Nailing 2/24/2020 Approved CHARLES BOGHOSKHAN
Green Building Rough 2/24/2020 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 2/24/2020 Approved CHARLES BOGHOSKHAN
Final 10/19/2020 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Not Ready HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/4/2020 Approved KATHRYN BUTTERWORTH
Final 12/4/2020 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/4/2020 Approved KATHRYN BUTTERWORTH
Green Building Final 12/4/2020 Approved KATHRYN BUTTERWORTH
MERV13>=Final 12/4/2020 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 12/4/2020 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 12/4/2020 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 12/4/2020 Approved KATHRYN BUTTERWORTH
Final 12/9/2020 Partial Inspection SCOTT FINNILA
Final 12/15/2020 Partial Inspection SCOTT FINNILA
Final 12/21/2020 Partial Approval SCOTT FINNILA
Final 1/19/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 10/25/2024 OK to Issue CofO HAMIK HARTOUNIAN