15076 W COBALT ST 91342
Certificate Information: 15076 W COBALT ST 91342
- Application / Permit
- 19014-20000-04928
- Plan Check / Job No.
- B19VN15207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 10'-2" X 20' BREEZEWAY TO DETACH EXISTING GARAGE; ADD 23' X 42'-6" IRREGULAR SHAPED TO AND CONVERT GARAGE TO ACCESSORY DWELING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 11/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2019 | SELLA BENYAMIN |
| Corrections Issued | 9/10/2019 | SELLA BENYAMIN |
| Building Plans Picked Up | 9/10/2019 | APPLICANT |
| Applicant returned to address corrections | 10/17/2019 | SELLA BENYAMIN |
| Applicant returned to address corrections | 11/18/2019 | SELLA BENYAMIN |
| Issued | 11/20/2019 | LADBS |
| CofO in Progress | 1/26/2021 | MISAEL ESPARZA |
| Permit Finaled | 3/19/2022 | RONALD MYRICK |
| CofO Issued | 3/19/2022 | RONALD MYRICK |
| Permit Finaled | 3/19/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/24/2019 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 10/1/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/3/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/10/2020 | Partial Approval | ROBERT MINASSIANS |
| Excavation/Setback/Form/Re-Bar | 2/12/2020 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/19/2020 | Approved | ROBERT MINASSIANS |
| Footing/Foundation/Slab | 2/19/2020 | Approved | ROBERT MINASSIANS |
| BUILDING-Rough-Frame | 3/11/2020 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 3/11/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/25/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/25/2020 | Approved | TROY SANDERS |
| Green Building Rough | 3/25/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 3/25/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/25/2020 | Approved | TROY SANDERS |
| Insulation | 3/27/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 4/1/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 4/1/2020 | Approved | TROY SANDERS |
| Final | 11/16/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 11/16/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 11/16/2020 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/18/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 12/18/2020 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/18/2020 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/18/2020 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 12/21/2020 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/25/2021 | Approved | MISAEL ESPARZA |
| Final | 1/25/2021 | OK to Issue CofO | MISAEL ESPARZA |
| HVAC-Final | 1/25/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 1/25/2021 | Approved | MISAEL ESPARZA |