8352 N COOPER PL 91306
Certificate Information: 8352 N COOPER PL 91306
- Application / Permit
- 19014-20000-04915
- Plan Check / Job No.
- B19VN15164
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21'-0" x 21'-6" IRREGULAR SHAPED ADDITION TO THE (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/17/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | ALDO UBAU |
| Corrections Issued | 11/7/2019 | ALDO UBAU |
| Applicant returned to address corrections | 11/22/2019 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/4/2019 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/17/2019 | SARKIS HARABEDIAN |
| Issued | 12/17/2019 | LADBS |
| CofO in Progress | 1/11/2024 | JEFFREY HARTLINE |
| Permit Finaled | 3/7/2024 | JOHN JANSON |
| CofO Issued | 3/7/2024 | JOHN JANSON |
| Permit Finaled | 3/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/12/2019 | HERMINIGILDO AGUSTIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2019 | APEKSHYA BAJRACHARYA |
| Miscellaneous | Cleared | 9/12/2019 | APEKSHYA BAJRACHARYA |
| Miscellaneous | Cleared | 9/12/2019 | HERMINIGILDO AGUSTIN |
| Private street | Cleared | 9/12/2019 | HERMINIGILDO AGUSTIN |
| Roof/Waste drainage to street | Cleared | 9/12/2019 | APEKSHYA BAJRACHARYA |
| Tract Map conditions | Cleared | 9/12/2019 | HERMINIGILDO AGUSTIN |
| Construction near power lines | Cleared | 11/3/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Monterrozo Construction Inc; Lic. No.: 1039434-B | P O BOX 16924 ENCINO, CA 91416 |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/4/2020 | No Access for Inspection | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 2/12/2020 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 2/19/2020 | Approved | PETER FOLLING |
| PLUMBING-Rough | 2/19/2020 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Partial Approval | HENRY KIM |
| Deputy Wood Construction | 3/26/2020 | Conditional Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2020 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 4/27/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 4/27/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 4/27/2020 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 4/27/2020 | Not Ready for Inspection | STEVEN BACK |
| Underground Mechanical | 4/27/2020 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 6/26/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 6/26/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 7/1/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 7/1/2020 | Approved | DAVID STEPANYAN |
| Insulation | 7/1/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 7/9/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 9/17/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/15/2023 | Approved | JEFFREY HARTLINE |
| Final | 12/15/2023 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 12/15/2023 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 12/15/2023 | Approved | JEFFREY HARTLINE |
| Verify Sprinkler Sign Off | 12/15/2023 | Approved | JEFFREY HARTLINE |
| Final | 1/10/2024 | OK to Issue CofO | JEFFREY HARTLINE |