5906 N OAKDALE AVE 91367

Certificate Information: 5906 N OAKDALE AVE 91367

Application / Permit
19014-20000-04912
Plan Check / Job No.
B19VN15156
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & IRREGULAR 1-STORY ADDITION TO (E) 1-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/9/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 NILOOFAR MEHRAIN
Corrections Issued 10/7/2019 NILOOFAR MEHRAIN
Quality Review Completed 10/8/2019 GUANG MIN TUNG
Green Plans Picked Up 10/10/2019 APPLICANT
Building Plans Picked Up 10/11/2019 APPLICANT
Plan Check Approved 1/2/2020 NILOOFAR MEHRAIN
Issued 1/9/2020 LADBS
CofO in Progress 2/11/2021 STEVEN BACK
CofO Issued 2/17/2021 DONALD SUNSERI
Permit Finaled 2/17/2021 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/19/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/19/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 12/24/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/24/2019 JEANIE LAM
Green Code Cleared 12/27/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 1/2/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 3/24/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 5/6/2020 Partial Approval STEVEN BACK
Underground Mechanical 5/6/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 5/12/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 5/26/2020 Corrections Issued STEVEN BACK
Deputy Drilled-In Anchors 5/28/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 5/28/2020 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 6/10/2020 Conditional Approval MICHAEL TEMPLE
Deputy Drilled-In Anchors 6/23/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Partial Approval STEVEN BACK
ELECTRICAL-Rough 8/25/2020 Corrections Issued STEVEN BACK
HVAC-Rough 8/25/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 8/31/2020 Approved STEVEN BACK
Deputy Drilled-In Anchors 8/31/2020 Approved STEVEN BACK
Deputy Wood Construction 8/31/2020 Approved STEVEN BACK
ELECTRICAL-Rough 8/31/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Approved STEVEN BACK
Green Building Rough 8/31/2020 Not Ready for Inspection STEVEN BACK
HVAC-Rough 8/31/2020 Approved STEVEN BACK
PLUMBING-Rough 8/31/2020 Approved STEVEN BACK
Green Building Rough 9/11/2020 Approved STEVEN BACK
Interior/Exterior Lathing 9/11/2020 Approved STEVEN BACK
Shower Pan 9/11/2020 Approved STEVEN BACK
Insulation 9/15/2020 Corrections Issued STEVEN BACK
Drywall Nailing 9/22/2020 Approved STEVEN BACK
Insulation 9/22/2020 Approved STEVEN BACK
Footing/Foundation/Slab 12/2/2020 Approved STEVEN BACK
Enclosure/Fence 1/4/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 2/11/2021 Approved STEVEN BACK
Final 2/11/2021 OK to Issue CofO STEVEN BACK
Green Building Final 2/11/2021 Approved STEVEN BACK
PLUMBING-Final 2/11/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Approved STEVEN BACK
Service/Power Release 2/11/2021 Approved STEVEN BACK
Smoke Detectors 2/11/2021 Approved STEVEN BACK