14146 W RAVEN ST 91342

Certificate Information: 14146 W RAVEN ST 91342

Application / Permit
19014-20000-04911
Plan Check / Job No.
B19VN15150
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 8' X 1.9" PORTION OF DETACHED GARAGE, ADD IRREGULAR SHAPE 31' X 40' AND CONVERT TO ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 2/10/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/5/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/18/2019 JENNIFER LEE
Corrections Issued 9/18/2019 JENNIFER LEE
Plan Check Approved 2/7/2020 ALDOUS CHIC
Issued 2/10/2020 LADBS
CofO in Progress 9/22/2020 MISAEL ESPARZA
Permit Finaled 10/5/2020 MICHAEL SMITH
CofO Issued 10/5/2020 MICHAEL SMITH
Permit Finaled 10/5/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/19/2019 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/22/2019 LEE GUILBEAUX
Sewer availability Cleared 10/22/2019 LEE GUILBEAUX
Low Impact Development Cleared 1/24/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/7/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/27/2020 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 3/3/2020 Corrections Issued DANIEL ORRANTE
Footing/Foundation/Slab 3/4/2020 Approved DANIEL ORRANTE
BUILDING-Rough-Frame 4/16/2020 Not Ready for Inspection TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 5/5/2020 Approved TROY SANDERS
Green Building Rough 5/5/2020 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 5/5/2020 Approved TROY SANDERS
Shower Pan 5/5/2020 Approved TROY SANDERS
Insulation 5/12/2020 Approved PIERRE VEGA
Interior/Exterior Lathing 5/12/2020 Corrections Issued PIERRE VEGA
Interior/Exterior Lathing 5/14/2020 Approved DANIEL ORRANTE
Drywall Nailing 5/22/2020 Approved TROY SANDERS
ELECTRICAL-Rough 7/13/2020 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 8/4/2020 Corrections Issued MISAEL ESPARZA
Final 8/27/2020 Corrections Issued MISAEL ESPARZA
Green Building Final 8/27/2020 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/27/2020 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 8/27/2020 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 9/21/2020 Approved MISAEL ESPARZA
Final 9/21/2020 OK to Issue CofO MISAEL ESPARZA
Green Building Final 9/21/2020 Approved MISAEL ESPARZA
HVAC-Final 9/21/2020 Approved MISAEL ESPARZA
PLUMBING-Final 9/21/2020 Approved MISAEL ESPARZA
Smoke Detectors 9/21/2020 Approved MISAEL ESPARZA