2138-2140 N MORENO DR 90039

Certificate Information: 2138-2140 N MORENO DR 90039

Application / Permit
19014-20000-04908
Plan Check / Job No.
B19VN15134
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 13' X 10' BREEZEWAY AND 12' 11" X 25' 10" ACCESSORY DWELLING UNIT TO (E) SINGLE FAMILY DWELLING PER AB 494 & SB 229. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 1/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/6/2019 GURUNATH NESARAJAH
Corrections Issued 9/6/2019 GURUNATH NESARAJAH
Building Plans Picked Up 9/17/2019 APPLICANT
Plan Check Approved 12/26/2019 GURUNATH NESARAJAH
Issued 1/6/2020 LADBS
CofO in Progress 1/12/2021 HAMIK HARTOUNIAN
Permit Finaled 1/15/2021 DEROLD HAUFF
CofO Issued 1/15/2021 DEROLD HAUFF
Permit Finaled 1/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/26/2019 ELENA LOPEZ
BHO/Hillside ordinance Cleared 11/26/2019 ELENA LOPEZ
BHO/Hillside ordinance Cleared 11/26/2019 ELENA LOPEZ
BHO/Hillside ordinance Cleared 11/26/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 11/26/2019 ELENA LOPEZ
Sewer availability Cleared 11/26/2019 ELENA LOPEZ
Permit Cleared 12/6/2019 THOMAS LANG
Roof/Waste drainage to street Cleared 12/6/2019 THOMAS LANG
Grading Pre-Inspection Cleared 12/26/2019 GURUNATH NESARAJAH

Contact Information

Architect Hersey,, John P; Lic. No.: C25560 8067 WILLOW GLEN ROAD      LOS ANGELES, CA 90046
Engineer Amoroso,, Gregory Michael; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Zhuang,, Wenbin; Lic. No.: S5236 184 S ALTADENA DRIVE      PASADENA, CA 91107

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/9/2020 Conditional Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 2/10/2020 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 2/10/2020 Approved JOSEPH MCGARRY
Gas Test 2/10/2020 Approved JOSEPH MCGARRY
Underground Mechanical 2/10/2020 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 2/13/2020 Approved JOSEPH MCGARRY
Deputy Wood Construction 2/13/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 2/13/2020 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 2/13/2020 Partial Approval JOSEPH MCGARRY
Underground Mechanical 2/13/2020 Approved JOSEPH MCGARRY
Insulation 2/26/2020 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 2/26/2020 Partial Approval JOSEPH MCGARRY
Drywall Nailing 3/3/2020 Approved JOSEPH MCGARRY
Green Building Rough 3/3/2020 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/3/2020 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 4/1/2020 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/9/2020 Approved JOSEPH MCGARRY
Shower Pan 4/9/2020 Approved JOSEPH MCGARRY
Final 12/21/2020 Corrections Issued JOSEPH MCGARRY
Green Building Final 12/21/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/21/2020 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 12/21/2020 Approved JOSEPH MCGARRY
Final 1/6/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 1/8/2021 Approved HAMIK HARTOUNIAN
Final 1/8/2021 OK to Issue CofO HAMIK HARTOUNIAN
HVAC-Final 1/8/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Final 1/8/2021 Approved HAMIK HARTOUNIAN