18410 S EVELYN AVE 90248

Certificate Information: 18410 S EVELYN AVE 90248

Application / Permit
19014-20000-04886
Plan Check / Job No.
B19VN15085
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 17'-4" X 27'-5" FOR NEW BEDROOM AND FAMILY ROOM TO AN (E) 1-STORY SFD PER ENGINEERING AT REAR.
Permit Issued
Issued on 12/16/2019
Issuing Office
Valley
Current Status
Issued on 12/16/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/6/2019 JENNIFER LEE
Corrections Issued 9/6/2019 JENNIFER LEE
Applicant returned to address corrections 10/10/2019 HAYATO TSUCHIYA
Applicant returned to address corrections 12/12/2019 HAYATO TSUCHIYA
Issued 12/16/2019 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/10/2019 GUILLERMO PETRA
Low Impact Development Cleared 12/5/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 12/5/2019 ERIK BEASLEY
Sewer availability Cleared 12/5/2019 ERIK BEASLEY

Contact Information

Engineer Standley,, Craig Erick; Lic. No.: C87675 6631 MURIETTA AVE      LOS ANGELES, CA 91405

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/10/2020 Approved JOHN KLARIN
Green Building Rough 4/10/2020 Approved JOHN KLARIN
PLUMBING-Rough 4/10/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Approved EUGENE CASSIDY
Wood Frame 4/13/2020 Partial Approval EUGENE CASSIDY
Insulation 4/15/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 4/15/2020 Approved BRIAN CHRISTIAN
Shower Pan 5/4/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 6/4/2020 Not Ready for Inspection EUGENE CASSIDY
Drywall Nailing 6/4/2020 Approved EUGENE CASSIDY
Final 6/4/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 6/4/2020 Approved EUGENE CASSIDY
Green Building Final 6/4/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/4/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 6/4/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 7/24/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/24/2020 Approved EUGENE CASSIDY
Final 7/24/2020 Corrections Issued EUGENE CASSIDY
HVAC-Final 7/24/2020 Approved EUGENE CASSIDY
PLUMBING-Final 7/24/2020 Approved EUGENE CASSIDY
Smoke Detectors 7/24/2020 Approved EUGENE CASSIDY
Final 7/29/2020 Corrections Issued EUGENE CASSIDY