8042 N RHODES AVE 91605

Certificate Information: 8042 N RHODES AVE 91605

Application / Permit
19014-20000-04882
Plan Check / Job No.
B19VN15074
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 14' 5" X 24' TO REAR OF (E) SINGLE FAMILY DWELLING TO EXPAND BEDROOM WITH 1/2 BATHROM (ACCESSIBLE FROM OUTSIDE ONLY). ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 10/15/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/6/2019 HAYATO TSUCHIYA
Corrections Issued 9/6/2019 HAYATO TSUCHIYA
Plan Check Approved 9/13/2019 GURUNATH NESARAJAH
Issued 10/15/2019 LADBS
CofO in Progress 10/19/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 12/10/2022 MICHAEL SMITH
CofO Issued 12/10/2022 MICHAEL SMITH
Permit Finaled 12/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/13/2019 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/13/2019 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Khanjian,, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/17/2019 Corrections Issued JOHN HAYES
Green Building Rough 12/17/2019 Not Ready for Inspection JOHN HAYES
Pre-Inspection 2/28/2020 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/2/2020 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 4/2/2020 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 10/6/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 10/6/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/5/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 3/5/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 3/5/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 3/31/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 4/13/2021 Not Ready for Inspection JOHN HAYES
Wood Frame 4/20/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 3/30/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/30/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 3/30/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/30/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 4/7/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 4/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/11/2022 Partial Approval CHRISTOPHER DELLEFIELD
Gas Test 4/11/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 4/11/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 4/11/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/11/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 4/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/14/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 4/20/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/2/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/25/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/15/2022 Approved JENNIFER RABUCHIN
Final 9/15/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 9/15/2022 Approved JENNIFER RABUCHIN
Green Building Final 9/15/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/15/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 9/15/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/11/2022 Approved CHRISTOPHER DELLEFIELD
Final 10/11/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 10/11/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/11/2022 Approved CHRISTOPHER DELLEFIELD
Final 10/19/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD