8042 N RHODES AVE 91605
Certificate Information: 8042 N RHODES AVE 91605
- Application / Permit
- 19014-20000-04882
- Plan Check / Job No.
- B19VN15074
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 14' 5" X 24' TO REAR OF (E) SINGLE FAMILY DWELLING TO EXPAND BEDROOM WITH 1/2 BATHROM (ACCESSIBLE FROM OUTSIDE ONLY). ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 10/15/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2019 | HAYATO TSUCHIYA |
| Corrections Issued | 9/6/2019 | HAYATO TSUCHIYA |
| Plan Check Approved | 9/13/2019 | GURUNATH NESARAJAH |
| Issued | 10/15/2019 | LADBS |
| CofO in Progress | 10/19/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
| CofO Issued | 12/10/2022 | MICHAEL SMITH |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2019 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/13/2019 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/17/2019 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 12/17/2019 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 2/28/2020 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/2/2020 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 4/2/2020 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 10/6/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/6/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 3/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 3/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 3/31/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 4/13/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 4/20/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 3/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 3/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 3/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/7/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/7/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/11/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Gas Test | 4/11/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Insulation | 4/14/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/19/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | JENNIFER RABUCHIN |
| Final | 9/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/15/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 9/15/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/15/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/11/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 10/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/19/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |