931 E VICTORIA AVE 90291
Certificate Information: 931 E VICTORIA AVE 90291
- Application / Permit
- 19014-20000-04875
- Plan Check / Job No.
- B19VN15054
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 697 SF 2ND STORY ADDITION TO (E) DWELLING WITH OPEN DECK.
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/3/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | JEFFREY TANGONAN |
| Corrections Issued | 9/25/2019 | JEFFREY TANGONAN |
| Quality Review Completed | 9/25/2019 | STEVEN KIM |
| Building Plans Picked Up | 9/26/2019 | APPLICANT |
| Green Plans Picked Up | 9/26/2019 | APPLICANT |
| Applicant returned to address corrections | 11/8/2019 | JEFFREY TANGONAN |
| Plan Check Approved | 12/10/2019 | JEFFREY TANGONAN |
| Issued | 1/3/2020 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 10/31/2019 | AARON COSTA |
| Miscellaneous | Cleared | 10/31/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 10/31/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 10/31/2019 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 10/31/2019 | HERMINIGILDO AGUSTIN |
| Address approval | Cleared | 11/5/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2019 | JEANIE LAM |
| Low Impact Development | Cleared | 11/5/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | JEANIE LAM |
| Sewer availability | Cleared | 11/5/2019 | JEANIE LAM |
| Specific Plan | Cleared | 11/19/2019 | BINDU KANNAN |
| ZI | Cleared | 11/19/2019 | BINDU KANNAN |
| Coastal Zone | Cleared | 12/10/2019 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 184 S ALTADENA DRIVE PASADENA, CA 91107 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/27/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 2/11/2020 | Partial Approval | DAVID HEINE |
| Wood Frame | 2/25/2020 | Partial Approval | DAVID HEINE |
| Drywall Nailing | 3/2/2020 | Approved | DAVID HEINE |
| Green Building Rough | 3/2/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 4/17/2020 | Partial Approval | DAVID HEINE |
| Wood Frame | 4/17/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 4/29/2020 | Approved | DAVID HEINE |
| Insulation | 5/1/2020 | Approved | DAVID HEINE |
| Shower Pan | 5/11/2020 | Approved | DAVID HEINE |
| Final | 8/7/2020 | Conditional Approval | DAVID HEINE |
| Footing/Foundation/Slab | 8/7/2020 | Approved | DAVID HEINE |
| Green Building Final | 8/7/2020 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 8/7/2020 | SGSOV Approved | DAVID HEINE |
| Smoke Detectors | 8/7/2020 | Approved | DAVID HEINE |
| Final | 9/18/2020 | Conditional Approval | DAVID HEINE |