9603 N HAYVENHURST PL 91343
Certificate Information: 9603 N HAYVENHURST PL 91343
- Application / Permit
- 19014-20000-04861
- Plan Check / Job No.
- B19VN15019
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION of detached Garage to Accessory Dwelling Unit AB 494 and SB 229. ADDITION of 21' x 21'2". Framed three bedrooms, two full bathrooms, living room, dining room kitchen, and laundry room. WORK PER WFPP.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | LUIS RINCON |
| Corrections Issued | 9/5/2019 | LUIS RINCON |
| Building Plans Picked Up | 9/10/2019 | APPLICANT |
| Plan Check Approved | 2/18/2020 | LUIS RINCON |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 12/6/2023 | RAUL OLAGI |
| Permit Finaled | 2/15/2024 | RUBEN SALAS |
| CofO Issued | 2/15/2024 | RUBEN SALAS |
| Permit Finaled | 2/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 1/22/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/22/2020 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 2/5/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/23/2022 | Not Ready for Inspection | RAUL OLAGI |
| Sewer | 3/23/2022 | Corrections Issued | RAUL OLAGI |
| Pre-Inspection | 3/29/2022 | Corrections Issued | RAUL OLAGI |
| Sewer | 5/5/2022 | Partial Inspection | RAUL OLAGI |
| Special/Order Compliance | 6/9/2022 | Corrections Issued | ALAN MORELOS |
| Underground Mechanical | 6/9/2022 | Partial Approval | ALAN MORELOS |
| Footing/Foundation/Slab | 9/27/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 9/27/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Partial Approval | RAUL OLAGI |
| Deputy Wood Construction | 12/15/2022 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 4/24/2023 | No Access for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/25/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 5/25/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 5/25/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 5/25/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/25/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 5/25/2023 | Approved | RAUL OLAGI |
| Insulation | 6/5/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 6/29/2023 | Approved | RAUL OLAGI |
| Shower Pan | 6/29/2023 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 7/24/2023 | Approved | RAUL OLAGI |
| Shower Pan | 7/24/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/1/2023 | Corrections Issued | RAUL OLAGI |
| Final | 12/1/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 12/1/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 12/1/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 12/1/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 12/1/2023 | Approved | RAUL OLAGI |
| Final | 12/6/2023 | OK to Issue CofO | RAUL OLAGI |