17071 W COUNTESS PL 91436

Certificate Information: 17071 W COUNTESS PL 91436

Application / Permit
19014-20000-04860
Plan Check / Job No.
B19VN15018
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF MASTER BEDROOM (21'-3" X 20'-3") W/ ROOFTOP DECK ABOVE TO (E) SFD W/ ATTACHED GARAGE; INTERIOR REMODEL
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 2/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2019 APPLICANT
Green Plans Picked Up 9/18/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 NILOOFAR MEHRAIN
Corrections Issued 9/23/2019 NILOOFAR MEHRAIN
Quality Review Completed 9/24/2019 GUANG MIN TUNG
Building Plans Picked Up 9/25/2019 APPLICANT
Applicant returned to address corrections 6/30/2020 NILOOFAR MEHRAIN
Plan Check Approved 9/22/2020 NILOOFAR MEHRAIN
Issued 1/12/2021 APPLICANT
CofO in Progress 2/12/2026 SEAN WIRCH
Permit Finaled 2/28/2026 MICHAEL PELHAM
CofO Issued 2/28/2026 MICHAEL PELHAM
Permit Finaled 2/28/2026 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/9/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 10/9/2019 ADRIAN CASTRO
Sewer availability Cleared 10/9/2019 ADRIAN CASTRO
ZA Case Cleared 10/9/2019 RINA LARA
Green Code Cleared 3/25/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 6/3/2020 KURT CORRAL
Grading Pre-Inspection Cleared 11/17/2020 NILOOFAR MEHRAIN

Contact Information

Contractor Mc Noon Crystal Import Inc; Lic. No.: 737529-B 1401 S ROBERTSON BLVD      LOS ANGELES, CA 90035
Engineer Lee,, Richard C C; Lic. No.: S1371 19558 GAULT ST      RESEDA, CA 91335

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/1/2021 Not Ready for Inspection RONALD COWAN
Green Building Rough 2/1/2021 Not Ready for Inspection RONALD COWAN
BUILDING-Rough-Frame 3/9/2021 Corrections Issued RONALD COWAN
Green Building Rough 3/9/2021 Corrections Issued RONALD COWAN
Footing/Foundation/Slab 4/16/2021 Approved RONALD COWAN
ELECTRICAL-Rough 9/2/2025 Approved SEAN WIRCH
HVAC-Rough 9/2/2025 Approved SEAN WIRCH
PLUMBING-Rough 9/2/2025 Approved SEAN WIRCH
Pre-Inspection 9/2/2025 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 11/19/2025 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 11/19/2025 Approved SEAN WIRCH
Green Building Rough 11/19/2025 Approved SEAN WIRCH
Insulation 11/19/2025 Not Ready for Inspection SEAN WIRCH
ELECTRICAL-Final 1/30/2026 Approved SEAN WIRCH
Final 2/13/2026 OK to Issue CofO SEAN WIRCH
Green Building Final 2/13/2026 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved SEAN WIRCH
Smoke Detectors 2/13/2026 Approved SEAN WIRCH