3752 S BEETHOVEN ST 90066

Certificate Information: 3752 S BEETHOVEN ST 90066

Application / Permit
19014-20000-04835
Plan Check / Job No.
B19VN14944
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL: REMOVE AND REFAME 1,421 SQFT OF EX DWELLING EXCEPT FOR 1' OF WALL/FOUNDATION TO REMAIN. ADD 844 SQFT OF FLOOR AREA AND 2-CAR GARAGE. ALL WORK PER ENGINEERING, ENTIRE BUILDING TO BE FULLY SPRINKLERED
Permit Issued
Issued on 1/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 JEFFREY TANGONAN
Green Plans Picked Up 9/17/2019 APPLICANT
Corrections Issued 9/18/2019 JEFFREY TANGONAN
Quality Review Completed 9/19/2019 STEVEN KIM
Building Plans Picked Up 9/20/2019 APPLICANT
Applicant returned to address corrections 10/8/2019 JEFFREY TANGONAN
Plan Check Approved 11/5/2019 JEFFREY TANGONAN
Issued 1/13/2020 LADBS
Refund Completed-Status Void 1/13/2021 SELENIA GARCIA
Re-Activate Permit 8/4/2021 CANDICE JUSAY
CofO in Progress 4/8/2022 RICHARD STEINBACH
Permit Finaled 4/13/2022 DANIEL ORRANTE
CofO Issued 4/13/2022 DANIEL ORRANTE
Permit Finaled 4/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/26/2019 NIKTA MOUSAVI
Sewer availability Cleared 9/26/2019 NIKTA MOUSAVI
Address approval Cleared 9/27/2019 JEANETTE VONG
Hydrant and Access approval Cleared 9/27/2019 JOHN CONNEALLY
Permit Cleared 9/27/2019 JEANETTE VONG
Green Code Cleared 10/10/2019 DAVID MATSON
Low Impact Development Cleared 10/15/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 10/15/2019 ELAINE LEI
Trees in Parkway Cleared 10/24/2019 JOHN KIM
GPI Written Notices Cleared 11/5/2019 JEFFREY TANGONAN
Grading Pre-Inspection Cleared 11/5/2019 JEFFREY TANGONAN

Contact Information

Contractor A1 Builders Inc; Lic. No.: 1031190-B 5900 SEPULVEDA BLVD   SUITE 102-08    SHERMAN OAKS, CA 91411
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/14/2020 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 1/21/2020 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 1/27/2020 Approved JOHNNY MIRANDA
Wood Frame 5/6/2020 Not Ready for Inspection DAVID FEILER
Wood Frame 5/13/2020 Corrections Issued DAVID FEILER
Wood Frame 5/15/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 6/2/2020 Partial Approval DAVID FEILER
Wood Frame 6/24/2020 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 8/12/2020 Corrections Issued JUAN VALENZUELA
HVAC-Rough 8/12/2020 Corrections Issued JUAN VALENZUELA
Deputy Wood Construction 8/14/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 8/25/2020 Not Ready for Inspection MATT KELLERMAN
HVAC-Rough 8/25/2020 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Rough 8/25/2020 Not Ready for Inspection MATT KELLERMAN
ELECTRICAL-Rough 8/27/2020 Not Ready for Inspection MATT KELLERMAN
HVAC-Rough 8/27/2020 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Rough 8/27/2020 Not Ready for Inspection MATT KELLERMAN
Interior/Exterior Lathing 9/8/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 9/9/2020 Not Ready for Inspection DAVID HEINE
ELECTRICAL-Rough 9/9/2020 Corrections Issued DAVID HEINE
Green Building Rough 9/9/2020 Not Ready for Inspection DAVID HEINE
HVAC-Rough 9/9/2020 Approved DAVID HEINE
PLUMBING-Rough 9/9/2020 Corrections Issued DAVID HEINE
BUILDING-Rough-Frame 9/15/2020 Not Ready for Inspection DAVID HEINE
ELECTRICAL-Rough 9/15/2020 Approved DAVID HEINE
Green Building Rough 9/15/2020 Not Ready for Inspection DAVID HEINE
HVAC-Rough 9/15/2020 Corrections Issued DAVID HEINE
PLUMBING-Rough 9/15/2020 Corrections Issued DAVID HEINE
ELECTRICAL-Rough 9/16/2020 Approved DAVID HEINE
HVAC-Rough 9/16/2020 Corrections Issued DAVID HEINE
PLUMBING-Rough 9/16/2020 Not Ready for Inspection DAVID HEINE
BUILDING-Rough-Frame 9/18/2020 Approved DAVID HEINE
Green Building Rough 9/18/2020 Approved DAVID HEINE
HVAC-Rough 9/18/2020 Approved DAVID HEINE
PLUMBING-Rough 9/18/2020 Approved DAVID HEINE
Insulation 9/28/2020 Approved ENRIQUE MIRELES
Drywall Nailing 10/8/2020 Approved ENRIQUE MIRELES
Shower Pan 11/23/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/9/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/24/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 8/9/2021 Partial Inspection JUAN VALENZUELA
PLUMBING-Final 8/9/2021 Corrections Issued JUAN VALENZUELA
Gas Test 8/13/2021 Approved ENRIQUE MIRELES
Service/Power Release 8/13/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/30/2022 Approved RICHARD STEINBACH
Final 3/30/2022 Corrections Issued RICHARD STEINBACH
Green Building Final 3/30/2022 Approved RICHARD STEINBACH
HVAC-Final 3/30/2022 Approved RICHARD STEINBACH
PLUMBING-Final 3/30/2022 Approved RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Approved RICHARD STEINBACH
Smoke Detectors 3/30/2022 Approved RICHARD STEINBACH
Final 4/8/2022 OK to Issue CofO RICHARD STEINBACH