4357 W 11TH ST 90019

Certificate Information: 4357 W 11TH ST 90019

Application / Permit
19014-20000-04721
Plan Check / Job No.
B19VN14574
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREGULAR SHAPE 31.5' X 25.5' ACCESSORY DWELLING UNIT ATTACHED TO DETACHED GARAGE PER AB494 & S229. ALL WORKS ARE PER WFPP
Permit Issued
Issued on 11/27/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 ALDOUS CHIC
Corrections Issued 8/29/2019 ALDOUS CHIC
Plan Check Approved 11/27/2019 KEVIN MORALES
Issued 11/27/2019 LADBS
CofO in Progress 10/26/2021 STUART CHAPMAN
Permit Finaled 11/15/2021 DEROLD HAUFF
CofO Issued 11/15/2021 DEROLD HAUFF
Permit Finaled 11/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/29/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/29/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 8/29/2019 JEANETTE VONG
Sewer availability Cleared 8/29/2019 JEANETTE VONG
Flood clearance Cleared 11/26/2019 TUYEN LE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 1/14/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/14/2020 Corrections Issued JOAQUIN GREENOUGH
METHANE-Barrier 1/14/2020 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 1/14/2020 Not Ready for Inspection JOAQUIN GREENOUGH
FLOOD-Elevation Certificate 1/29/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/29/2020 Corrections Issued JOAQUIN GREENOUGH
METHANE-Barrier 1/29/2020 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 1/29/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 2/3/2020 Approved AJA COLLAY
FLOOD-Proofing Certificate 2/3/2020 Approved AJA COLLAY
Green Building Rough 2/3/2020 Not Ready for Inspection AJA COLLAY
METHANE-Rough 2/3/2020 Approved AJA COLLAY
BUILDING-Rough-Frame 5/20/2020 Partial Approval STUART CHAPMAN
Green Building Rough 5/20/2020 Not Ready for Inspection STUART CHAPMAN
Wood Frame 5/20/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2020 Not Ready for Inspection STUART CHAPMAN
Insulation 5/26/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 9/28/2020 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 11/24/2020 Approved STUART CHAPMAN
PLUMBING-Rough 11/24/2020 Approved STUART CHAPMAN
Wood Frame 11/24/2020 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 12/28/2020 Conditional Approval STUART CHAPMAN
Green Building Rough 12/28/2020 Approved STUART CHAPMAN
Insulation 1/5/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 1/5/2021 Partial Approval STUART CHAPMAN
Drywall Nailing 1/14/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 1/14/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/10/2021 Approved STUART CHAPMAN
FLOOD-Elevation Certificate 6/10/2021 Approved STUART CHAPMAN
Final 6/10/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 6/10/2021 Approved STUART CHAPMAN
Green Building Final 6/10/2021 Approved STUART CHAPMAN
METHANE-Barrier 6/10/2021 Approved STUART CHAPMAN
METHANE-Subgrade 6/10/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved STUART CHAPMAN
Service/Power Release 6/10/2021 Approved STUART CHAPMAN
Smoke Detectors 6/10/2021 Approved STUART CHAPMAN
Final 8/20/2021 Not Ready for Inspection STUART CHAPMAN
Final 10/26/2021 OK to Issue CofO STUART CHAPMAN