6320 W 85TH ST 90045

Certificate Information: 6320 W 85TH ST 90045

Application / Permit
19014-20000-04710
Plan Check / Job No.
B19VN14536
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2ND FLOOR ADD'N, CONSIST OF 2-BEDROOMS/CLOSETS & FULL BATHROOM TO (E) SFD W/ATT. 2-CAR GARAGE & REMODEL AT 1ST FLOOR NEW BATHROOM & CONVERT BEDROOM TO FAMILY ROOM..
Permit Issued
Issued on 1/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 ABDUL CHEGENI
Green Plans Picked Up 9/26/2019 APPLICANT
Corrections Issued 10/8/2019 ABDUL CHEGENI
Quality Review Completed 10/9/2019 STEVEN KIM
Building Plans Picked Up 10/10/2019 APPLICANT
Plan Check Approved 11/14/2019 ABDUL CHEGENI
Issued 1/14/2020 LADBS
CofO in Progress 9/2/2020 JUAN VALENZUELA
Permit Finaled 5/4/2022 DANIEL ORRANTE
CofO Issued 5/4/2022 DANIEL ORRANTE
Permit Finaled 5/4/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/10/2019 GUILLERMO PETRA
Sewer availability Cleared 10/10/2019 GUILLERMO PETRA
Green Code Cleared 11/13/2019 MICHAEL AYERS
Low Impact Development Cleared 11/14/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/14/2019 APEKSHYA BAJRACHARYA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Butel Construction Inc; Lic. No.: 852273-B 257 SOUTH CITRUS AVE      LOS ANGELES, CA 90036
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/14/2020 Approved MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 3/23/2020 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 3/23/2020 Approved JOHNNY MIRANDA
Green Building Rough 3/23/2020 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 3/23/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 3/23/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/24/2020 Partial Inspection JUAN VALENZUELA
HVAC-Rough 3/27/2020 Approved JOHNNY MIRANDA
Shower Pan 3/27/2020 Approved JOHNNY MIRANDA
Insulation 4/1/2020 Approved JOHNNY MIRANDA
Drywall Nailing 4/7/2020 Approved JOHNNY MIRANDA
Green Building Rough 4/7/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 4/7/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 6/10/2020 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 6/10/2020 Corrections Issued JUAN VALENZUELA
Final 6/10/2020 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 6/10/2020 Corrections Issued JUAN VALENZUELA
HVAC-Final 6/10/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 6/10/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 6/10/2020 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 7/14/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Final 7/14/2020 Approved JOHNNY MIRANDA
Final 7/14/2020 Corrections Issued JOHNNY MIRANDA
Green Building Final 7/14/2020 Partial Inspection JOHNNY MIRANDA
HVAC-Final 7/14/2020 Approved JOHNNY MIRANDA
Smoke Detectors 7/14/2020 Approved JOHNNY MIRANDA
Final 9/1/2020 OK to Issue CofO JUAN VALENZUELA
Green Building Final 9/1/2020 Approved JUAN VALENZUELA