18235 W WELBY WAY 91335
Certificate Information: 18235 W WELBY WAY 91335
- Application / Permit
- 19014-20000-04705
- Plan Check / Job No.
- B19VN14520
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 17'-0" X 30'-0" DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/7/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/31/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2019 | JENNIFER LEE |
| Corrections Issued | 9/6/2019 | JENNIFER LEE |
| Plan Check Approved | 1/7/2020 | JENNIFER LEE |
| Issued | 1/7/2020 | LADBS |
| CofO in Progress | 7/28/2020 | VINCENT HANLEY |
| Permit Finaled | 7/31/2020 | DONALD SUNSERI |
| CofO Issued | 7/31/2020 | DONALD SUNSERI |
| Permit Finaled | 7/31/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/23/2019 | RIDWAN HARDY |
| Address approval | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/5/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 12/18/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 12/20/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/3/2020 | MARKOS PEREZ-BRAN |
| Public Works-Sewers | Cleared | 1/3/2020 | MARKOS PEREZ-BRAN |
| Public Works-Open Permits | Cleared | 1/3/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/28/2020 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 2/10/2020 | Approved | DAVID SCANTLIN |
| Sewer | 2/20/2020 | Partial Approval | VINCENT HANLEY |
| Gas Test | 2/25/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/25/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/25/2020 | Approved | VINCENT HANLEY |
| Underground Mechanical | 2/25/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2020 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 4/7/2020 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/16/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/16/2020 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 4/16/2020 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/6/2020 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Final | 5/6/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/6/2020 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 5/6/2020 | Approved | VINCENT HANLEY |
| Wood Frame | 5/6/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/13/2020 | Partial Approval | VINCENT HANLEY |
| Insulation | 5/18/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/21/2020 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 5/21/2020 | Partial Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 7/16/2020 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Final | 7/16/2020 | Approved | VINCENT HANLEY |
| Final | 7/16/2020 | Not Ready for Inspection | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/16/2020 | Approved | VINCENT HANLEY |
| Gas Test | 7/16/2020 | Approved | VINCENT HANLEY |
| Green Building Final | 7/16/2020 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/16/2020 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 7/16/2020 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/16/2020 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 7/16/2020 | Approved | VINCENT HANLEY |
| Smoke Detectors | 7/16/2020 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 7/16/2020 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/23/2020 | Approved | VINCENT HANLEY |
| Final | 7/23/2020 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 7/23/2020 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/23/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/23/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/23/2020 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 7/23/2020 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 7/23/2020 | Not Ready for Inspection | VINCENT HANLEY |