18235 W WELBY WAY 91335

Certificate Information: 18235 W WELBY WAY 91335

Application / Permit
19014-20000-04705
Plan Check / Job No.
B19VN14520
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 17'-0" X 30'-0" DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 1/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2019 APPLICANT
Assigned to Plan Check Engineer 9/6/2019 JENNIFER LEE
Corrections Issued 9/6/2019 JENNIFER LEE
Plan Check Approved 1/7/2020 JENNIFER LEE
Issued 1/7/2020 LADBS
CofO in Progress 7/28/2020 VINCENT HANLEY
Permit Finaled 7/31/2020 DONALD SUNSERI
CofO Issued 7/31/2020 DONALD SUNSERI
Permit Finaled 7/31/2020 DONALD SUNSERI

Permit Application Clearance Information

Construction near power lines Cleared 10/23/2019 RIDWAN HARDY
Address approval Cleared 11/5/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/5/2019 ADRIAN CASTRO
Sewer availability Cleared 11/5/2019 ADRIAN CASTRO
Green Code Cleared 12/18/2019 MICHAEL AYERS
Low Impact Development Cleared 12/20/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/3/2020 MARKOS PEREZ-BRAN
Public Works-Sewers Cleared 1/3/2020 MARKOS PEREZ-BRAN
Public Works-Open Permits Cleared 1/3/2020 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2020 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/10/2020 Approved DAVID SCANTLIN
Sewer 2/20/2020 Partial Approval VINCENT HANLEY
Gas Test 2/25/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 2/25/2020 Partial Approval VINCENT HANLEY
Sewer 2/25/2020 Approved VINCENT HANLEY
Underground Mechanical 2/25/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/28/2020 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Not Ready for Inspection VINCENT HANLEY
Wood Frame 4/7/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 4/16/2020 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 4/16/2020 Partial Approval VINCENT HANLEY
Wood Frame 4/16/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/6/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 5/6/2020 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Approved VINCENT HANLEY
Green Building Rough 5/6/2020 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 5/6/2020 Approved VINCENT HANLEY
Wood Frame 5/6/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/13/2020 Partial Approval VINCENT HANLEY
Insulation 5/18/2020 Approved VINCENT HANLEY
Drywall Nailing 5/21/2020 Approved MICHAEL TEMPLE
Interior/Exterior Lathing 5/21/2020 Partial Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 7/16/2020 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 7/16/2020 Approved VINCENT HANLEY
Final 7/16/2020 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 7/16/2020 Approved VINCENT HANLEY
Gas Test 7/16/2020 Approved VINCENT HANLEY
Green Building Final 7/16/2020 Approved VINCENT HANLEY
HVAC-Final 7/16/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Final 7/16/2020 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/16/2020 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 7/16/2020 Approved VINCENT HANLEY
Smoke Detectors 7/16/2020 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/16/2020 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 7/23/2020 Approved VINCENT HANLEY
Final 7/23/2020 OK to Issue CofO VINCENT HANLEY
Gas Test 7/23/2020 Approved VINCENT HANLEY
HVAC-Final 7/23/2020 Approved VINCENT HANLEY
PLUMBING-Final 7/23/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/23/2020 SGSOV Approved VINCENT HANLEY
Service/Power Release 7/23/2020 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/23/2020 Not Ready for Inspection VINCENT HANLEY