12017 W LAUREL TERRACE DR 91604

Certificate Information: 12017 W LAUREL TERRACE DR 91604

Application / Permit
19014-20000-04704
Plan Check / Job No.
B19VN14518
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
38' x 45' SECOND STORY ADDITION; ADD 18'-2" X 20'-2" OPEN TRELLIS ON SECOND FLOOR; ADD 21'-5" X 22' IRREGULAR SHAPED GARAGE TO FIRST FLOOR; CONVERT (E) BEDROOM TO GARAGE; INTERIOR REMODEL
Permit Issued
Issued on 1/16/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2019 APPLICANT
Assigned to Plan Check Engineer 9/12/2019 SELLA BENYAMIN
Corrections Issued 9/17/2019 SELLA BENYAMIN
Quality Review Completed 9/19/2019 STEVEN KIM
Building Plans Picked Up 9/23/2019 APPLICANT
Applicant returned to address corrections 11/4/2019 SELLA BENYAMIN
Plan Check Approved 12/4/2019 SELLA BENYAMIN
Issued 1/16/2020 LADBS
CofO in Progress 4/13/2021 ARAM AVEDISIAN
Permit Finaled 1/8/2022 MICHAEL SMITH
CofO Issued 1/8/2022 MICHAEL SMITH
Permit Finaled 1/8/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/25/2019 GUILLERMO PETRA
Permit Cleared 9/25/2019 GUILLERMO PETRA
Sewer availability Cleared 9/25/2019 GUILLERMO PETRA
Green Code Cleared 9/26/2019 MICHAEL AYERS
Low Impact Development Cleared 10/24/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/24/2019 ELAINE LEI
Grading Pre-Inspection Cleared 10/25/2019 PATRICK MISCHLICH
ZA Case Cleared 10/25/2019 DIANA JIMENEZ
GPI Written Notices Cleared 12/4/2019 SELLA BENYAMIN

Contact Information

Contractor Arg Builders Inc; Lic. No.: 1033233-B 11209 NATIONAL BLVD #406      LOS ANGELES, CA 90064
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/31/2020 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 2/5/2020 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 2/11/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 2/21/2020 Partial Approval ARAM AVEDISIAN
Green Building Rough 2/21/2020 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 7/1/2020 Approved ARAM AVEDISIAN
HVAC-Rough 7/1/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/1/2020 Approved ARAM AVEDISIAN
Insulation 8/12/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 8/12/2020 Partial Approval ARAM AVEDISIAN
Drywall Nailing 8/18/2020 Approved DANIEL ORRANTE
Shower Pan 9/2/2020 Corrections Issued ARAM AVEDISIAN
Shower Pan 9/8/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/11/2020 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 9/15/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/21/2020 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 12/21/2020 Corrections Issued ARAM AVEDISIAN
Service/Power Release 12/21/2020 Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/28/2020 Approved ARAM AVEDISIAN
PLUMBING-Final 1/12/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/1/2021 Approved ARAM AVEDISIAN
Final 3/1/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 3/1/2021 Approved ARAM AVEDISIAN
Green Building Final 3/1/2021 Approved ARAM AVEDISIAN
Green Building Rough 3/1/2021 Approved ARAM AVEDISIAN
HVAC-Final 3/1/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/1/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 3/1/2021 Approved ARAM AVEDISIAN
Final 4/13/2021 OK to Issue CofO ARAM AVEDISIAN