3355 W PERLITA AVE 90039
Certificate Information: 3355 W PERLITA AVE 90039
- Application / Permit
- 19014-20000-04691
- Plan Check / Job No.
- B19VN14473
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21'-0" X 21'-0" DETACHED GARAGE AND ADD 18'-0" X 29'-6" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2019 | JENNIFER LEE |
| Corrections Issued | 9/6/2019 | JENNIFER LEE |
| Plan Check Approved | 1/15/2020 | ROSENDO MEDINA |
| Issued | 1/15/2020 | LADBS |
| CofO in Progress | 1/8/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 1/12/2021 | DEROLD HAUFF |
| CofO Issued | 1/12/2021 | DEROLD HAUFF |
| Permit Finaled | 1/12/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/7/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/7/2019 | RIDWAN HARDY |
| Address approval | Cleared | 12/30/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/30/2019 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 12/31/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/31/2019 | THOMAS LANG |
Contact Information
| Contractor | Pathi Plumbing & Construction Inc; Lic. No.: 756445-B | 2412 NORTH LINCOLN STREET BURBANK, CA 91504 |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/17/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/27/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 1/27/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 2/10/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/3/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/3/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/3/2020 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/3/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/3/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/10/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 4/10/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/10/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/10/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 4/17/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/17/2020 | Approved | HAMIK HARTOUNIAN |
| Sewer | 4/17/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/28/2020 | Approved | OSVALDO PARAMO |
| Gas Test | 4/28/2020 | Conditional Approval | OSVALDO PARAMO |
| Green Building Rough | 4/28/2020 | Approved | OSVALDO PARAMO |
| Final | 10/5/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/5/2020 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 10/5/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 10/5/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/5/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 1/7/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |