1840 W 11TH PL 90006
Certificate Information: 1840 W 11TH PL 90006
- Application / Permit
- 19014-20000-04669
- Plan Check / Job No.
- B19VN14425
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (2) Duplex
- Work Description
- CONVERT FOUR (E) GUEST ROOMS INTO THREE (N) LIGHT HOUSEKEEPING UNITS OF (E) DUPLEX W/ 4-GUEST ROOM BUILDING; ADD (1) STANDARD PKG STALL
- Permit Issued
- Issued on 8/7/2020
- Issuing Office
- Current Status
- CofO Issued on 1/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2019 | APPLICANT |
| Green Plans Picked Up | 9/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/16/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/18/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 9/23/2019 | APPLICANT |
| Plan Check Approved | 4/9/2020 | NILOOFAR MEHRAIN |
| Issued | 8/7/2020 | APPLICANT |
| CofO in Progress | 11/10/2021 | KATHRYN BUTTERWORTH |
| No Progress | 11/19/2021 | SCOTT FINNILA |
| CofO in Progress | 1/11/2022 | TERRY HERR |
| CofO Issued | 1/11/2022 | TERRY HERR |
| Permit Finaled | 1/11/2022 | TERRY HERR |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2019 | THOMAS LANG |
| CPC | Cleared | 11/14/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 11/14/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/14/2019 | THOMAS LANG |
| Green Code | Cleared | 11/21/2019 | AARON COSTA |
| HPOZ | Cleared | 3/19/2020 | DANIEL MATA |
| Project located in CRA area | Cleared | 3/19/2020 | DANIEL MATA |
| ZI | Cleared | 3/19/2020 | DANIEL MATA |
| ZI | Cleared | 3/19/2020 | DANIEL MATA |
| ZI | Cleared | 3/19/2020 | DANIEL MATA |
Contact Information
| Contractor | Caribe Construction Inc; Lic. No.: 878090-B | 521 PARISH PLACE BURBANK, CA 91506 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/10/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 10/1/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 2/12/2021 | Corrections Issued | SCOTT FINNILA |
| METHANE-Rough | 2/12/2021 | Approved | SCOTT FINNILA |
| Wood Frame | 2/12/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 2/26/2021 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 2/26/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 3/4/2021 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 3/19/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 6/8/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 9/20/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 9/20/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 9/20/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Final | 10/6/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Final | 10/6/2021 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Not Ready | ROBERT VORHIS |
| Smoke Detectors | 10/6/2021 | Corrections Issued | ROBERT VORHIS |
| Final | 11/5/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 11/5/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 11/5/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 11/22/2021 | Corrections Issued | KATHRYN BUTTERWORTH |