13647 W JUDD ST 91331

Certificate Information: 13647 W JUDD ST 91331

Application / Permit
19014-20000-04662
Plan Check / Job No.
B19VN14418
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20'-6" X 24'-0" ACCESSORY DWELLING UNIT ADDITION PER AB 494 & SB 229 TO EXISTING DETACHED REC ROOM
Permit Issued
Issued on 6/9/2020
Issuing Office
Current Status
CofO Issued on 4/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2019 APPLICANT
Assigned to Plan Check Engineer 8/27/2019 JEROME MAGAT PALMA
Corrections Issued 8/28/2019 JEROME MAGAT PALMA
Building Plans Picked Up 8/28/2019 APPLICANT
Plan Check Approved 5/26/2020 JEROME MAGAT PALMA
Issued 6/9/2020 APPLICANT
CofO in Progress 3/12/2021 MICHEL ABAJAN
CofO Issued 4/29/2021 MICHAEL SMITH
Permit Finaled 4/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 4/3/2020 RIDWAN HARDY
Address approval Cleared 4/23/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 4/23/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/27/2020 RENZ SORIANO
Sewer availability Cleared 4/30/2020 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/11/2020 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 8/11/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 8/11/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 8/11/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 8/14/2020 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 9/1/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/14/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 9/14/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 9/14/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/16/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/16/2020 Approved MICHEL ABAJAN
Green Building Rough 11/16/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 11/16/2020 Approved MICHEL ABAJAN
Drywall Nailing 12/22/2020 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 12/22/2020 Not Ready for Inspection JOHN HAYES
Insulation 1/21/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/21/2021 Approved MICHEL ABAJAN
Drywall Nailing 1/22/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 2/24/2021 Approved MICHEL ABAJAN
Final 2/24/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 2/24/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 2/24/2021 Approved MICHEL ABAJAN
PLUMBING-Final 2/24/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 2/24/2021 Approved MICHEL ABAJAN
Final 3/12/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 3/12/2021 Approved MICHEL ABAJAN