11451 W SYLVAN ST 91606
Certificate Information: 11451 W SYLVAN ST 91606
- Application / Permit
- 19014-20000-04659
- Plan Check / Job No.
- B19VN14410
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2ND STORY ADDITION & CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT, 1187 SF OF ACCESSORY DWELLING UNIT + 130 SF OF STORAGE, PER AB 494 SB 229. PER ENGINEERING WORK.
- Permit Issued
- Issued on 7/6/2020
- Issuing Office
- Current Status
- Issued on 7/6/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/27/2019 | APPLICANT |
| Green Plans Picked Up | 9/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | PARISA ZAHABI |
| Corrections Issued | 10/7/2019 | PARISA ZAHABI |
| Quality Review Completed | 10/8/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 10/11/2019 | APPLICANT |
| Plan Check Approved | 2/14/2020 | PARISA ZAHABI |
| Issued | 7/6/2020 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/6/2019 | RIDWAN HARDY |
| Address approval | Cleared | 11/22/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2019 | THOMAS LANG |
| Low Impact Development | Cleared | 11/22/2019 | ORVAL HERNANDEZ-MARCIAL |
| Permit | Cleared | 11/22/2019 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 11/22/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/22/2019 | THOMAS LANG |
| Green Code | Cleared | 2/11/2020 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2021 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 6/24/2021 | Partial Approval | DANIEL DREW |
| Deputy Drilled-In Anchors | 6/30/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 6/30/2021 | Approved | DANIEL DREW |
| Special/Order Compliance | 10/27/2021 | Corrections Issued | MICHAEL PELHAM |
| Green Building Rough | 3/31/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 3/31/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 4/7/2022 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/12/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/12/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/12/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 4/12/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/18/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 4/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 4/22/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 4/29/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/6/2022 | Approved | CALEB MEISTER |
| Insulation | 5/9/2022 | Corrections Issued | ALAN MORELOS |
| Insulation | 5/12/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 5/19/2022 | Approved | CALEB MEISTER |
| Shower Pan | 5/26/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/2/2022 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 9/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 9/23/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 10/5/2022 | Approved | JOHN HAYES |
| PLUMBING-Final | 10/5/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/10/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 11/10/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/6/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 2/6/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/6/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 2/6/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/6/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/6/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/18/2026 | Approved | DAVID ANDERSON |
| Final | 2/18/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/18/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 2/18/2026 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 2/18/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Pre-Inspection | 3/10/2026 | Approved | ROBERTO PALACIOS-LOPEZ |