19427-19429 W MAYALL ST 91324
Certificate Information: 19427-19429 W MAYALL ST 91324
- Application / Permit
- 19014-20000-04568
- Plan Check / Job No.
- B19VN14145
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 26'-8" X 20'-6" ADDITION TO AND CONVERT PORTION OF (E) SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT (1199 SQ FT) PER AB 494 AND SB 229
- Permit Issued
- Issued on 2/7/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/23/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 8/26/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/4/2019 | APPLICANT |
| Plan Check Approved | 2/7/2020 | JEROME MAGAT PALMA |
| Issued | 2/7/2020 | LADBS |
| CofO in Progress | 1/10/2024 | DAVID SCANTLIN |
| Permit Finaled | 3/8/2024 | JOHN JANSON |
| CofO Issued | 3/8/2024 | JOHN JANSON |
| Permit Finaled | 3/8/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 1/28/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/28/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/27/2020 | Conditional Approval | HENRY KIM |
| PLUMBING-Rough | 3/27/2020 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2020 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 4/17/2020 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 4/27/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 4/27/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/27/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/27/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/27/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 4/27/2020 | Approved | VINCENT HANLEY |
| Insulation | 4/29/2020 | Approved | DONALD SUNSERI |
| Interior/Exterior Lathing | 4/29/2020 | Corrections Issued | DONALD SUNSERI |
| Shower Pan | 4/29/2020 | Corrections Issued | DONALD SUNSERI |
| Drywall Nailing | 5/7/2020 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 5/7/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/7/2020 | Approved | HENRY KIM |
| Shower Pan | 5/7/2020 | Approved | HENRY KIM |
| Final | 5/26/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 5/26/2021 | Not Ready for Inspection | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 5/26/2021 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 5/26/2021 | Not Ready for Inspection | HENRY KIM |
| Final | 6/8/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 6/8/2021 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 6/8/2021 | Approved | JEFFREY PARD |
| Final | 6/23/2021 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 6/23/2021 | Not Ready for Inspection | JEFFREY PARD |
| Final | 12/5/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 12/5/2023 | Approved | DAVID SCANTLIN |
| Final | 12/15/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Inspection | 12/19/2023 | Approved | DAVID SCANTLIN |
| Final | 12/27/2023 | Corrections Issued | JOHN KIDWELL |
| Final | 1/10/2024 | OK to Issue CofO | DAVID SCANTLIN |