6825 N CALHOUN AVE 91405

Certificate Information: 6825 N CALHOUN AVE 91405

Application / Permit
19014-20000-04563
Plan Check / Job No.
B19VN14132
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' 6" X 12' 9" PORTION OF (E) 2-CAR GARAGE TO ACCESSORY DWELLING UNIT, REMOVE 20' 6" X 5' 9" PORTION OF DETACHED GARAGE AND ADD 20' 6" X 22' 9" 2-STORY IRR.-SHAPE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 3/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2019 APPLICANT
Assigned to Plan Check Engineer 8/23/2019 GURUNATH NESARAJAH
Corrections Issued 8/23/2019 GURUNATH NESARAJAH
Building Plans Picked Up 10/29/2019 APPLICANT
Plan Check Approved 3/4/2020 GURUNATH NESARAJAH
Issued 3/11/2020 LADBS
CofO in Progress 5/24/2024 RYAN SALAZAR
Permit Finaled 9/5/2024 DANIEL ORRANTE
CofO Issued 9/5/2024 DANIEL ORRANTE
Permit Finaled 9/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/8/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/8/2020 GABRIEL ROBLES
Sewer availability Cleared 1/8/2020 GABRIEL ROBLES
Low Impact Development Cleared 2/10/2020 MITESH PATEL
Green Code Cleared 2/20/2020 MICHAEL AYERS
Roof/Waste drainage to street Cleared 3/4/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/13/2020 Corrections Issued MISAEL ESPARZA
Sewer 7/13/2020 Approved MISAEL ESPARZA
Footing/Foundation/Slab 10/13/2020 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Partial Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/17/2021 Corrections Issued MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Corrections Issued MICHAEL TEMPLE
HVAC-Rough 3/17/2021 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 3/17/2021 Approved MICHAEL TEMPLE
ELECTRICAL-Rough 4/21/2021 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 4/21/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 6/22/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/22/2021 Partial Approval ARTHUR SARGSYAN
HVAC-Rough 6/22/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 7/14/2021 Approved ASHLEY THOMPSON
Green Building Rough 7/14/2021 Approved ASHLEY THOMPSON
Pre-Inspection 7/14/2021 Partial Inspection CALEB MEISTER
Smoke Detectors 7/14/2021 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV Not Ready RICHARD DOCKUS
ELECTRICAL-Final 5/22/2023 Corrections Issued RYAN SALAZAR
ELECTRICAL-Final 8/15/2023 Not Ready for Inspection RYAN SALAZAR
Final 10/3/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 3/22/2024 Corrections Issued RYAN SALAZAR
Final 3/22/2024 Not Ready for Inspection RYAN SALAZAR
Green Building Final 3/22/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 3/22/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/14/2024 Approved RYAN SALAZAR
Final 5/14/2024 Partial Approval RYAN SALAZAR
Service/Power Release 5/14/2024 Approved RYAN SALAZAR
Final 5/23/2024 OK to Issue CofO RYAN SALAZAR
Service/Power Release 5/23/2024 Approved RYAN SALAZAR