2475 N ECHO PARK AVE 90026

Certificate Information: 2475 N ECHO PARK AVE 90026

Application / Permit
19014-20000-04562
Plan Check / Job No.
B19VN14128
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 33'11" X 27'(738 SQ.FT.) IRREGULAR SHAPED STORAGE ROOM AT 1ST FLOOR TO BE PART OF SFD TO CREATE NEW DEN , NEW BEDROOM, NEW STUDY ROOM , (1) NEW BATHROOM , RELOCATE LAUNDRY, INTERIOR REMODEL TO (E) SFD TO 2ND FLOOR TO ADD NEW STAIRCASE BETWEEN FLOORS , CREATE NEW POWDER ROOM , REMOVE (1) BATHROOM , REMODEL (2) BEDROOMS, ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 RARES BODEA
Corrections Issued 9/9/2019 RARES BODEA
Quality Review Completed 9/12/2019 GUANG MIN TUNG
Building Plans Picked Up 9/13/2019 APPLICANT
Green Plans Picked Up 9/13/2019 APPLICANT
Applicant returned to address corrections 11/5/2019 RARES BODEA
Plan Check Approved 12/16/2019 RARES BODEA
Issued 1/14/2020 LADBS
CofO in Progress 12/21/2020 COREY HUPP
CofO in Progress 12/21/2020 COREY HUPP
Permit Finaled 12/24/2020 DEROLD HAUFF
CofO Issued 12/24/2020 DEROLD HAUFF
Permit Finaled 12/24/2020 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 12/5/2019 AARON COSTA
Distance to fire station Cleared 12/16/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 12/16/2019 ADRIAN CASTRO
Grading Pre-Inspection Cleared 12/16/2019 RARES BODEA
Hydrant and Access approval Cleared 12/16/2019 GEORGE SUCHAND
Sewer availability Cleared 12/16/2019 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/12/2020 Partial Approval AJA COLLAY
Deputy Drilled-In Anchors 3/31/2020 Partial Approval RUBEN SALAS
Masonry Wall/Backfill 4/2/2020 Off-Hour Fees Due
PLUMBING-Rough 4/2/2020 Off-Hour Fees Due
Footing/Foundation/Slab 4/6/2020 Partial Approval HAMIK HARTOUNIAN
Masonry Wall/Backfill 4/6/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 4/6/2020 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/13/2020 Approved KATHRYN BUTTERWORTH
Masonry Wall/Backfill 4/13/2020 Approved KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 4/24/2020 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 6/19/2020 Partial Approval COREY HUPP
Rough-Elec/Plmb/HVAC 6/19/2020 Partial Approval COREY HUPP
ELECTRICAL-Rough 6/23/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 6/23/2020 Approved KATHRYN BUTTERWORTH
Insulation 6/29/2020 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 7/14/2020 Approved STUART CHAPMAN
Green Building Rough 7/14/2020 Approved STUART CHAPMAN
Wood Frame 7/14/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/21/2020 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 8/21/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 8/25/2020 Approved DAVID MATSON
Shower Pan 8/25/2020 Not Ready for Inspection DAVID MATSON
Shower Pan 8/26/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/6/2020 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 10/14/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 10/30/2020 Approved COREY HUPP
Final 10/30/2020 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 10/30/2020 SGSOV Not Required COREY HUPP
Smoke Detectors 10/30/2020 Not Ready for Inspection COREY HUPP
Final 11/5/2020 OK to Issue CofO COREY HUPP
Green Building Final 11/5/2020 Approved COREY HUPP
Smoke Detectors 11/5/2020 Approved COREY HUPP