10844 N LANGMUIR AVE 91040
Certificate Information: 10844 N LANGMUIR AVE 91040
- Application / Permit
- 19014-20000-04510
- Plan Check / Job No.
- B19VN13968
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 44' X 41' IRR.-SHAPE TO 1ST STORY AND 44' X 16' SECOND STORY TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 10/23/2020
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 9/3/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 9/5/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 9/5/2019 | APPLICANT |
| Green Plans Picked Up | 9/5/2019 | APPLICANT |
| Plan Check Approved | 10/5/2020 | GURUNATH NESARAJAH |
| Issued | 10/23/2020 | APPLICANT |
| CofO in Progress | 4/22/2022 | MATTHEW NELSON |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 10/15/2019 | DAVID MATSON |
| Miscellaneous | Cleared | 10/21/2019 | SAFA JAVANMARDI |
| ZI | Cleared | 10/21/2019 | DAISY BENICIA |
| Low Impact Development | Cleared | 2/14/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/21/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/27/2020 | GABRIEL ROBLES |
| GPI Written Notices | Cleared | 9/18/2020 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 9/18/2020 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Farag,, Amgad N; Lic. No.: C74076 | 27050 MAPLE TREE CT VALENCIA, CA 91381 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/31/2020 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 10/31/2020 | Partial Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 11/9/2020 | Not Ready for Inspection | DAVID MATSON |
| Footing/Foundation/Slab | 11/9/2020 | Not Ready for Inspection | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 11/13/2020 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 11/13/2020 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 11/13/2020 | Off-Hour Fees Due | |
| Underground Mechanical | 11/13/2020 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 1/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/11/2021 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 7/1/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 7/1/2021 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 7/2/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/12/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 7/12/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/12/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/10/2021 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 8/23/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/23/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/8/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/8/2021 | Approved | MATTHEW NELSON |
| Shower Pan | 10/18/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 12/21/2021 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/21/2021 | SGSOV Approved | MATTHEW NELSON |
| Final | 4/20/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/20/2022 | Approved | MATTHEW NELSON |
| Green Building Final | 4/20/2022 | Approved | MATTHEW NELSON |
| Smoke Detectors | 4/20/2022 | Approved | MATTHEW NELSON |
| Final | 4/22/2022 | OK to Issue CofO | MATTHEW NELSON |