8223 N CORBIN AVE 91306
Certificate Information: 8223 N CORBIN AVE 91306
- Application / Permit
- 19014-20000-04468
- Plan Check / Job No.
- B19VN13815
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 4' X 20'1" PORTION OF (E) GARAGE ,CONVERT (E) 14' X 20'1" DETACHED GARAGE TO ACCESSORY DWELLING UNIT AND ADD 7'1" X 11'1" TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 8/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2019 | ANGELICA DAVE |
| Corrections Issued | 8/16/2019 | ANGELICA DAVE |
| Applicant returned to address corrections | 8/20/2019 | RARES BODEA |
| Plan Check Approved | 8/20/2019 | GURUNATH NESARAJAH |
| Issued | 8/20/2019 | LADBS |
| CofO in Progress | 3/31/2021 | HENRY KIM |
| CofO Issued | 4/27/2021 | JOHN JANSON |
| Permit Finaled | 4/27/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/16/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 8/16/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2019 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/20/2019 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2019 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 10/16/2019 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 11/25/2019 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Green Building Rough | 11/25/2019 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 1/17/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/21/2020 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 3/2/2020 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 3/2/2020 | Corrections Issued | HENRY KIM |
| Green Building Rough | 3/2/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 3/2/2020 | Approved | HENRY KIM |
| Sewer | 3/2/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 3/17/2020 | Partial Approval | HENRY KIM |
| Insulation | 3/17/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 3/17/2020 | Partial Approval | HENRY KIM |
| Underground Mechanical | 3/17/2020 | Not Ready for Inspection | HENRY KIM |
| Drywall Nailing | 4/8/2020 | Approved | HENRY KIM |
| Underground Mechanical | 5/29/2020 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 6/5/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 6/5/2020 | Approved | HENRY KIM |
| Sewer | 6/5/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 8/19/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Final | 10/2/2020 | Corrections Issued | HENRY KIM |
| Final | 10/2/2020 | Corrections Issued | HENRY KIM |
| Green Building Final | 10/2/2020 | Approved | HENRY KIM |
| HVAC-Final | 10/2/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 10/2/2020 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 10/2/2020 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 10/2/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 11/16/2020 | Not Ready for Inspection | HENRY KIM |
| Final | 11/16/2020 | Not Ready for Inspection | HENRY KIM |
| HVAC-Final | 11/16/2020 | Not Ready for Inspection | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 11/16/2020 | SGSOV Not Ready | HENRY KIM |
| ELECTRICAL-Final | 2/11/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 2/11/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 2/11/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 3/10/2021 | Approved | HENRY KIM |
| Final | 3/10/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 3/10/2021 | Corrections Issued | HENRY KIM |
| HVAC-Final | 3/10/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 3/10/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 3/10/2021 | SGSOV Not Ready | HENRY KIM |
| Final | 3/31/2021 | OK to Issue CofO | HENRY KIM |
| Gas Test | 3/31/2021 | Approved | HENRY KIM |
| HVAC-Final | 3/31/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 3/31/2021 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | HENRY KIM |