7226 N RUBIO AVE 91406

Certificate Information: 7226 N RUBIO AVE 91406

Application / Permit
19014-20000-04449
Plan Check / Job No.
B19VN13750
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13' x 15' laundry and closet addition to single family dwelling and add 26' x 11' living room extension. Work per wfpp.
Permit Issued
Issued on 8/26/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2019 APPLICANT
Assigned to Plan Check Engineer 8/26/2019 SELLA BENYAMIN
Issued 8/26/2019 LADBS
CofO in Progress 7/30/2020 JACK KARGODORIAN
CofO Issued 8/11/2020 MICHAEL SMITH
Permit Finaled 8/11/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/26/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 8/26/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Yaghoubi M Corp; Lic. No.: 972773-B 6459 LUBAO AVENUE      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2019 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/10/2019 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 10/10/2019 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/10/2019 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 10/10/2019 Approved JACK KARGODORIAN
Insulation 10/10/2019 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 10/10/2019 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 10/10/2019 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 10/21/2019 Approved JACK KARGODORIAN
ELECTRICAL-Rough 10/23/2019 Approved JACK KARGODORIAN
Drywall Nailing 10/28/2019 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/5/2019 Approved JACK KARGODORIAN
Final 1/10/2020 Corrections Issued JACK KARGODORIAN
Green Building Final 1/10/2020 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/10/2020 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 1/10/2020 Approved JACK KARGODORIAN
Final 2/25/2020 Conditional Approval JACK KARGODORIAN