3708 S RUTHELEN ST 90018
Certificate Information: 3708 S RUTHELEN ST 90018
- Application / Permit
- 19014-20000-04381
- Plan Check / Job No.
- B19VN13538
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 7' X 16' FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/31/2019
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/31/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2019 | JENNIFER LEE |
| Corrections Issued | 8/15/2019 | JENNIFER LEE |
| Building Plans Picked Up | 8/15/2019 | APPLICANT |
| Plan Check Approved | 10/31/2019 | JENNIFER LEE |
| Issued | 10/31/2019 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 8/19/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/19/2019 | LEE GUILBEAUX |
| ZI | Cleared | 8/19/2019 | STEVEN WECHSLER |
| Construction near power lines | Cleared | 10/18/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/18/2019 | RIDWAN HARDY |
Contact Information
| Contractor | K T Construction & Development; Lic. No.: 1031495-B | 137 SOUTH ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/29/2019 | Partial Inspection | ROBERT VORHIS |
| Pre-Inspection | 12/5/2019 | Approved | ROBERT MCDOWELL |
| Pre-Inspection | 1/22/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 2/21/2020 | Not Ready for Inspection | HORACE FULTZ |
| Sewer | 2/21/2020 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 2/27/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 2/27/2020 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 2/27/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/26/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/26/2020 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 3/26/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 3/26/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/26/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2020 | Approved | DAVID CHAN |
| Rough-Elec/Plmb/HVAC | 4/1/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 4/8/2020 | Approved | JUSTIN CURTIS |
| Green Building Rough | 4/8/2020 | Approved | JUSTIN CURTIS |
| HVAC-Rough | 4/8/2020 | Approved | JUSTIN CURTIS |
| Interior/Exterior Lathing | 4/8/2020 | Approved | JUSTIN CURTIS |
| Insulation | 4/14/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/21/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 4/21/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/19/2020 | Approved | ROBERT MCDOWELL |
| Gas Test | 5/19/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/19/2020 | Approved | ROBERT MCDOWELL |
| Sewer | 5/19/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 6/11/2020 | Approved | ROBERT MCDOWELL |
| Final | 6/11/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 6/11/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 6/11/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 6/11/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 6/11/2020 | SGSOV Not Ready | ROBERT MCDOWELL |
| Smoke Detectors | 6/11/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 6/19/2020 | Approved | ROBERT MCDOWELL |
| Final | 6/19/2020 | Conditional Approval | ROBERT MCDOWELL |
| HVAC-Final | 6/19/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 6/19/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 6/19/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 6/19/2020 | Approved | ROBERT MCDOWELL |
| Final | 4/22/2026 | Corrections Issued | SABAS ALONSO |