2900 S KERCKHOFF AVE 90731

Certificate Information: 2900 S KERCKHOFF AVE 90731

Application / Permit
19014-20000-04361
Plan Check / Job No.
B19VN13480
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Enclose existing Patio Cover and reframe roof, complete interior remodel of single-family dwelling, and addition of 15' x 21' adding a bedroom and full bathroom. Work per WFPP.
Permit Issued
Issued on 10/18/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2019 APPLICANT
Assigned to Plan Check Engineer 8/12/2019 ALDOUS CHIC
Corrections Issued 8/12/2019 ALDOUS CHIC
Applicant returned to address corrections 10/10/2019 ANGELICA DAVE
Applicant returned to address corrections 10/15/2019 PINANK PATEL
Applicant returned to address corrections 10/16/2019 LUIS RINCON
Plan Check Approved 10/16/2019 LUIS RINCON
Issued 10/18/2019 LADBS
CofO in Progress 10/31/2024 JOSEPH MCGARRY
Permit Finaled 10/31/2024 ANSON MAGLASANG
CofO Issued 10/31/2024 ANSON MAGLASANG
Permit Finaled 10/31/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 8/13/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/13/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 8/13/2019 GUILLERMO PETRA
Sewer availability Cleared 8/13/2019 GUILLERMO PETRA
Specific Plan Cleared 8/15/2019 STEVEN WECHSLER
ZI Cleared 8/15/2019 STEVEN WECHSLER
Coastal Zone Cleared 10/10/2019 STEVEN WECHSLER
Grading Pre-Inspection Cleared 10/10/2019 ALDOUS CHIC

Contact Information

Contractor Ezra Meir; Lic. No.: 1050037-B 269 S BEVERLY DR #103      BEVERLY HILLS, CA 90212

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/24/2019 Conditional Approval ANDREW BEELI
Footing/Foundation/Slab 1/7/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/22/2020 Corrections Issued ANSON MAGLASANG
Green Building Rough 1/22/2020 Corrections Issued ANSON MAGLASANG
Insulation 1/22/2020 Not Ready for Inspection ANSON MAGLASANG
Sewer 1/22/2020 Not Ready for Inspection ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Partial Approval ANSON MAGLASANG
Insulation 2/12/2020 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 2/12/2020 Partial Approval ANSON MAGLASANG
Sewer 2/12/2020 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Corrections Issued ANSON MAGLASANG
PLUMBING-Rough 3/4/2020 Corrections Issued ANSON MAGLASANG
Sewer 3/4/2020 Corrections Issued ANSON MAGLASANG
BUILDING-Rough-Frame 4/24/2020 Partial Inspection JOHN KLARIN
Insulation 4/24/2020 Partial Inspection JOHN KLARIN
ELECTRICAL-Rough 10/7/2020 Not Ready for Inspection JOHN KLARIN
HVAC-Rough 10/7/2020 Approved JOHN KLARIN
PLUMBING-Rough 10/7/2020 Approved JOHN KLARIN
Wood Frame 10/7/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 10/13/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Approved JOHN KLARIN
Gas Test 10/13/2020 Approved JOHN KLARIN
Shower Pan 10/13/2020 Approved JOHN KLARIN
Wood Frame 10/13/2020 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 11/10/2020 Approved JOHN KLARIN
Green Building Rough 11/10/2020 Approved JOHN KLARIN
Insulation 11/10/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 11/10/2020 Approved JOHN KLARIN
Wood Frame 11/10/2020 Approved JOHN KLARIN
Drywall Nailing 11/17/2020 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 11/17/2020 Not Ready for Inspection JOHN KLARIN
Special/Order Compliance 12/21/2020 Approved JOHN KLARIN
Drywall Nailing 4/22/2024 Not Ready for Inspection ANSON MAGLASANG
Final 4/22/2024 Corrections Issued ANSON MAGLASANG
Green Building Final 4/22/2024 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 4/22/2024 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 4/22/2024 Approved ANSON MAGLASANG
Drywall Nailing 9/30/2024 Approved JOSEPH MCGARRY
Final 9/30/2024 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready JOSEPH MCGARRY
Final 10/30/2024 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Approved JOSEPH MCGARRY