21601-21603 W BLACKHAWK ST 91311
Certificate Information: 21601-21603 W BLACKHAWK ST 91311
- Application / Permit
- 19014-20000-04346
- Plan Check / Job No.
- B19VN13425
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 15' X 41' ATTACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER WFPP
- Permit Issued
- Issued on 10/7/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2019 | ALDOUS CHIC |
| Corrections Issued | 8/12/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 9/17/2019 | RAPHAEL ROSAS |
| Plan Check Approved | 10/1/2019 | ALDOUS CHIC |
| Issued | 10/7/2019 | LADBS |
| CofO in Progress | 2/17/2021 | DAVID STEPANYAN |
| Permit Finaled | 2/19/2021 | JOHN JANSON |
| CofO Issued | 2/19/2021 | JOHN JANSON |
| Permit Finaled | 2/19/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2019 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2019 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/19/2019 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 9/17/2019 | ALDOUS CHIC |
| Low Impact Development | Cleared | 9/17/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/17/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/18/2019 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 11/23/2019 | Corrections Issued | JOSEPH SAGEN |
| Footing/Foundation/Slab | 12/5/2019 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 1/7/2020 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 1/7/2020 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2020 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 5/20/2020 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 5/20/2020 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2020 | Approved | DAVID STEPANYAN |
| Gas Test | 5/20/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 5/20/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 5/20/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 5/20/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/10/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 6/10/2020 | Approved | DAVID STEPANYAN |
| Insulation | 6/10/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/10/2020 | Partial Approval | DAVID STEPANYAN |
| Shower Pan | 6/10/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 6/12/2020 | Partial Approval | DAVID STEPANYAN |
| Drywall Nailing | 6/17/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/17/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 11/12/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 11/12/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 11/12/2020 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 11/12/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Final | 11/12/2020 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Service/Power Release | 11/12/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Smoke Detectors | 11/12/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 2/17/2021 | Approved | DAVID STEPANYAN |
| Final | 2/17/2021 | OK to Issue CofO | DAVID STEPANYAN |
| Gas Test | 2/17/2021 | Approved | DAVID STEPANYAN |
| Green Building Final | 2/17/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 2/17/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 2/17/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 2/17/2021 | SGSOV Approved | DAVID STEPANYAN |
| Service/Power Release | 2/17/2021 | Approved | DAVID STEPANYAN |