4838 N QUEDO PL 91364
Certificate Information: 4838 N QUEDO PL 91364
- Application / Permit
- 19014-20000-04330
- Plan Check / Job No.
- B19VN13369
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 18' X 18' KITCHEN EXTENSION TO REAR OF (E) SFD W/ GARAGE AND ADD 11'X26'-5" OPEN TRELLIS_ ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 9/10/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2019 | PINANK PATEL |
| Corrections Issued | 8/12/2019 | PINANK PATEL |
| Applicant returned to address corrections | 8/13/2019 | RARES BODEA |
| Applicant returned to address corrections | 8/14/2019 | DAWN MC NULTY |
| Plan Check Approved | 8/28/2019 | SARKIS HARABEDIAN |
| Issued | 9/10/2019 | LADBS |
| CofO in Progress | 3/11/2021 | DAVID SANDOVAL |
| CofO Issued | 3/12/2021 | RONALD MYRICK |
| Permit Finaled | 3/12/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 8/12/2019 | APEKSHYA BAJRACHARYA |
| Grading Pre-Inspection | Cleared | 8/13/2019 | PINANK PATEL |
| GPI Written Notices | Cleared | 8/28/2019 | DAWN MC NULTY |
Contact Information
| Contractor | Odm Construction Inc; Lic. No.: 1050851-B | 7800 ORION AVENUE VAN NUYS, CA 91406 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/22/2019 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/4/2019 | Corrections Issued | JOHN JANSON |
| Footing/Foundation/Slab | 11/18/2019 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2020 | Corrections Issued | JOHN JANSON |
| Deputy Wood Construction | 1/16/2020 | Approved | JOHN JANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2020 | Partial Approval | JOHN JANSON |
| BUILDING-Rough-Frame | 3/5/2020 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Approved | PETER FOLLING |
| HVAC-Rough | 3/5/2020 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 3/25/2020 | Corrections Issued | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 3/25/2020 | Corrections Issued | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 4/1/2020 | Approved | MICHAEL TEMPLE |
| Green Building Rough | 4/1/2020 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 4/1/2020 | Approved | MICHAEL TEMPLE |
| Rough-Elec/Plmb/HVAC | 4/1/2020 | Approved | MICHAEL TEMPLE |
| Insulation | 4/7/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 4/15/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 4/17/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 4/21/2020 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 11/13/2020 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Not Ready | STEVEN BACK |
| Pre-Inspection | 12/14/2020 | Corrections Issued | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/8/2021 | Approved | DAVID SANDOVAL |
| Final | 3/8/2021 | OK to Issue CofO | DAVID SANDOVAL |
| Green Building Final | 3/8/2021 | Approved | DAVID SANDOVAL |
| HVAC-Final | 3/8/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 3/8/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/8/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 3/8/2021 | Approved | DAVID SANDOVAL |