1418 S CARDIFF AVE 90035
Certificate Information: 1418 S CARDIFF AVE 90035
- Application / Permit
- 19014-20000-04329
- Plan Check / Job No.
- B19VN13366
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST & 2ND FLOOR ADDITIONS TO (E) 1-STORY SFD; INTERIOR REMODEL (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 1/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2019 | APPLICANT |
| Green Plans Picked Up | 8/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 8/26/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 8/27/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 9/9/2019 | APPLICANT |
| Applicant returned to address corrections | 10/24/2019 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/5/2019 | NILOOFAR MEHRAIN |
| Issued | 1/6/2020 | LADBS |
| CofO in Progress | 11/16/2021 | KENNETH NAGLE |
| Permit Finaled | 12/2/2021 | KENNETH NAGLE |
| CofO Issued | 12/2/2021 | KENNETH NAGLE |
| Permit Finaled | 12/2/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2019 | JOHN LIN |
| Low Impact Development | Cleared | 10/22/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/22/2019 | JOHN LIN |
| Sewer availability | Cleared | 10/22/2019 | JOHN LIN |
| Green Code | Cleared | 10/23/2019 | AARON COSTA |
| Hydrant and Access approval | Cleared | 10/23/2019 | GEORGE SUCHAND |
| GPI Written Notices | Cleared | 10/24/2019 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 10/24/2019 | NILOOFAR MEHRAIN |
Contact Information
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/27/2020 | Conditional Approval | RONALD WEBER |
| Footing/Foundation/Slab | 1/28/2020 | Conditional Approval | RONALD WEBER |
| Deputy Reinf. Concrete | 1/29/2020 | Conditional Approval | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Corrections Issued | RONALD WEBER |
| BUILDING-Rough-Frame | 2/26/2020 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/26/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2020 | Corrections Issued | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 4/23/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 4/23/2020 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2020 | Conditional Approval | KEVIN SARGSYAN |
| Green Building Rough | 5/12/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 5/12/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/12/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Wood Construction | 5/13/2020 | No Access for Inspection | KENNETH NAGLE |
| Green Building Final | 5/21/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 5/21/2020 | Approved | KEVIN SARGSYAN |
| METHANE-Rough | 5/21/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/21/2020 | Corrections Issued | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 5/21/2020 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 5/21/2020 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/27/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/27/2020 | Approved | KEVIN SARGSYAN |
| Green Building Final | 5/29/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/29/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 6/4/2020 | Approved | KEVIN SARGSYAN |
| Insulation | 6/4/2020 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/4/2020 | Approved | KEVIN SARGSYAN |
| Wood Frame | 6/4/2020 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 6/11/2020 | Approved | KEVIN SARGSYAN |
| Shower Pan | 6/16/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/19/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 6/19/2020 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 6/23/2020 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/26/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 2/4/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 6/11/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 6/11/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Final | 6/11/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/16/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/16/2021 | No Access for Inspection | KEVIN SARGSYAN |
| Final | 7/16/2021 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/16/2021 | Approved | KEVIN SARGSYAN |
| Green Building Final | 7/16/2021 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 7/16/2021 | No Access for Inspection | KEVIN SARGSYAN |
| METHANE-Barrier | 7/16/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 7/16/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 7/16/2021 | No Access for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 7/16/2021 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 7/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| Final | 7/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 7/20/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 7/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 7/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 7/20/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 9/13/2021 | Corrections Issued | KEVIN SARGSYAN |
| Final | 9/13/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 9/13/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 9/13/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/4/2021 | Approved | KEVIN SARGSYAN |
| Final | 11/4/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 11/4/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 11/4/2021 | Approved | KEVIN SARGSYAN |
| Final | 11/9/2021 | Conditional Approval | KEVIN SARGSYAN |