245 N ARDEN BLVD 90004

Certificate Information: 245 N ARDEN BLVD 90004

Application / Permit
19014-20000-04292
Plan Check / Job No.
B19VN13248
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19'-2" X 20'-11" DETACHED GARAGE AND ADD 11'-6" X 18'-11" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 JENNIFER LEE
Corrections Issued 8/15/2019 JENNIFER LEE
Applicant returned to address corrections 9/25/2019 ANGELICA DAVE
Plan Check Approved 10/15/2019 ANGELICA MARTINEZ
Issued 12/14/2020 APPLICANT
Building Plans Picked Up 12/16/2020 APPLICANT
CofO in Progress 3/29/2022 ARTHUR SARGSYAN
CofO in Progress 3/29/2022 ARTHUR SARGSYAN
Permit Finaled 2/23/2023 DANIEL ORRANTE
CofO Issued 2/23/2023 DANIEL ORRANTE
Permit Finaled 2/23/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/4/2019 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/4/2019 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/4/2019 GABRIEL ROBLES
Sewer availability Cleared 9/4/2019 GABRIEL ROBLES
CPC Cleared 9/9/2019 MAX LODER
CPC Cleared 9/9/2019 MAX LODER
HPOZ Cleared 9/9/2019 MAX LODER
Miscellaneous Cleared 9/9/2019 MAX LODER
ZI Cleared 9/11/2019 HERMINIGILDO AGUSTIN
ZI Cleared 9/11/2019 HERMINIGILDO AGUSTIN
Construction near power lines Cleared 9/25/2019 OSCAR CASTRO

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor Owner-Builder       ,
Engineer Janecek,, Alexander Mark; Lic. No.: C80579 2902 S MANSFIELD AVE      LOS ANGELES, CA 90016

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/5/2021 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 5/13/2021 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 5/28/2021 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/28/2021 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/23/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/23/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 6/23/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/30/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 6/30/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 7/15/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 7/15/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 7/15/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/30/2021 Corrections Issued ARTHUR SARGSYAN
HVAC-Rough 7/30/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 10/1/2021 Approved ARTHUR SARGSYAN
Green Building Rough 10/1/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 10/1/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 10/1/2021 Approved ARTHUR SARGSYAN
Wood Frame 10/1/2021 Approved ARTHUR SARGSYAN
Insulation 10/14/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 10/14/2021 Approved ARTHUR SARGSYAN
Shower Pan 10/14/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 10/28/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/23/2022 SGSOV Not Ready ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/3/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 3/3/2022 Approved ARTHUR SARGSYAN
Final 3/3/2022 Corrections Issued ARTHUR SARGSYAN
Green Building Final 3/3/2022 Approved ARTHUR SARGSYAN
HVAC-Final 3/3/2022 Approved ARTHUR SARGSYAN
PLUMBING-Final 3/3/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 3/3/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 3/25/2022 Off-Hour Fees Due
Final 3/25/2022 OK to Issue CofO ARTHUR SARGSYAN
Final 3/25/2022 Off-Hour Fees Due
HVAC-Final 3/25/2022 Off-Hour Fees Due
PLUMBING-Final 3/25/2022 Off-Hour Fees Due
Service/Power Release 3/29/2022 Approved ARTHUR SARGSYAN