245 N ARDEN BLVD 90004
Certificate Information: 245 N ARDEN BLVD 90004
- Application / Permit
- 19014-20000-04292
- Plan Check / Job No.
- B19VN13248
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'-2" X 20'-11" DETACHED GARAGE AND ADD 11'-6" X 18'-11" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/14/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | JENNIFER LEE |
| Corrections Issued | 8/15/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 9/25/2019 | ANGELICA DAVE |
| Plan Check Approved | 10/15/2019 | ANGELICA MARTINEZ |
| Issued | 12/14/2020 | APPLICANT |
| Building Plans Picked Up | 12/16/2020 | APPLICANT |
| CofO in Progress | 3/29/2022 | ARTHUR SARGSYAN |
| CofO in Progress | 3/29/2022 | ARTHUR SARGSYAN |
| Permit Finaled | 2/23/2023 | DANIEL ORRANTE |
| CofO Issued | 2/23/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/23/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2019 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2019 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/4/2019 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/4/2019 | GABRIEL ROBLES |
| CPC | Cleared | 9/9/2019 | MAX LODER |
| CPC | Cleared | 9/9/2019 | MAX LODER |
| HPOZ | Cleared | 9/9/2019 | MAX LODER |
| Miscellaneous | Cleared | 9/9/2019 | MAX LODER |
| ZI | Cleared | 9/11/2019 | HERMINIGILDO AGUSTIN |
| ZI | Cleared | 9/11/2019 | HERMINIGILDO AGUSTIN |
| Construction near power lines | Cleared | 9/25/2019 | OSCAR CASTRO |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Owner-Builder | , |
| Engineer | Janecek,, Alexander Mark; Lic. No.: C80579 | 2902 S MANSFIELD AVE LOS ANGELES, CA 90016 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2021 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 5/13/2021 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/28/2021 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 5/28/2021 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 6/23/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/30/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 6/30/2021 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/15/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 7/15/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 7/15/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/30/2021 | Corrections Issued | ARTHUR SARGSYAN |
| HVAC-Rough | 7/30/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 10/1/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 10/1/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 10/1/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 10/1/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 10/1/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 10/14/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 10/14/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 10/14/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 10/28/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Not Ready | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| Final | 3/3/2022 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Final | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/3/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/25/2022 | Off-Hour Fees Due | |
| Final | 3/25/2022 | OK to Issue CofO | ARTHUR SARGSYAN |
| Final | 3/25/2022 | Off-Hour Fees Due | |
| HVAC-Final | 3/25/2022 | Off-Hour Fees Due | |
| PLUMBING-Final | 3/25/2022 | Off-Hour Fees Due | |
| Service/Power Release | 3/29/2022 | Approved | ARTHUR SARGSYAN |