4461 N CALEDONIA WAY 90065

Certificate Information: 4461 N CALEDONIA WAY 90065

Application / Permit
19014-20000-04259
Plan Check / Job No.
B19VN13140
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD TO ENCLOSE 4' X 9-6" COVERED PATIO AND CONVERT 19-'3" X 21'-6" BASEMENT TO LIVING SPACE. REMODEL TO (E) SFD.
Permit Issued
Issued on 9/10/2020
Issuing Office
Valley
Current Status
Permit Finaled on 10/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 RAPHAEL ROSAS
Corrections Issued 8/24/2019 RAPHAEL ROSAS
Quality Review Completed 8/27/2019 CHON CHIO KUO
Green Plans Picked Up 9/4/2019 APPLICANT
Building Plans Picked Up 9/9/2019 APPLICANT
Applicant returned to address corrections 8/7/2020 RAPHAEL ROSAS
Applicant returned to address corrections 8/26/2020 RAPHAEL ROSAS
Plan Check Approved 9/2/2020 RAPHAEL ROSAS
Issued 9/10/2020 APPLICANT
Permit Finaled 10/30/2020 BRAD BESCOS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/2/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 1/2/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 1/2/2020 GUILLERMO PETRA
Distance to fire station Cleared 1/2/2020 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 1/2/2020 GUILLERMO PETRA
Sewer availability Cleared 1/2/2020 GUILLERMO PETRA
Grading Pre-Inspection Cleared 1/3/2020 KIRK LINKLATER
Green Code Cleared 1/16/2020 AARON COSTA
Supp. Use District POD/CDO/TDO Cleared 7/20/2020 MIGUEL GAMBOA
ZI Cleared 7/20/2020 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/10/2020 No Access for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 1/13/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 2/23/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/4/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 3/4/2021 Approved CRAIG VAUGHAN
HVAC-Rough 3/4/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 3/4/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/15/2021 Partial Approval CRAIG VAUGHAN
HVAC-Rough 3/15/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/16/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/24/2021 Approved HAMIK HARTOUNIAN
Insulation 3/24/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 4/13/2021 Approved THOMAS LOGRASSO
Shower Pan 5/19/2021 Approved THOMAS LOGRASSO
HVAC-Rough 5/27/2021 Not Ready for Inspection COREY HUPP
Interior/Exterior Lathing 5/27/2021 Approved COREY HUPP
HVAC-Rough 6/15/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 6/28/2021 Partial Approval HAMIK HARTOUNIAN
Pre-Inspection 6/28/2021 Partial Inspection ALAN MORELOS
ELECTRICAL-Final 8/19/2021 Corrections Issued CRAIG VAUGHAN
Final 8/19/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/19/2021 Approved CRAIG VAUGHAN
HVAC-Final 8/19/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 8/19/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/19/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/19/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 8/23/2021 Corrections Issued CRAIG VAUGHAN
Final 9/2/2021 Conditional Approval CRAIG VAUGHAN
Gas Test 9/2/2021 Approved CRAIG VAUGHAN
Smoke Detectors 9/2/2021 Approved CRAIG VAUGHAN