4517 E CLELAND AVE 90065
Certificate Information: 4517 E CLELAND AVE 90065
- Application / Permit
- 19014-20000-04248
- Plan Check / Job No.
- B19VN13098
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 12'-3" X 14'-6" AND 4'-3" X 4'-11" FOR BEDROOM/BATHROOM/CLOSET TO AN (E) 1-STORY SFD AND REMODEL THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2019 | JENNIFER LEE |
| Green Plans Picked Up | 8/22/2019 | APPLICANT |
| Corrections Issued | 8/29/2019 | JENNIFER LEE |
| Quality Review Completed | 8/29/2019 | STEVEN KIM |
| Building Plans Picked Up | 8/29/2019 | APPLICANT |
| Plan Check Approved | 1/27/2020 | ARTIN ZARUKIAN |
| Issued | 2/5/2020 | LADBS |
| CofO in Progress | 7/15/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 8/2/2022 | DEROLD HAUFF |
| CofO Issued | 8/2/2022 | DEROLD HAUFF |
| Permit Finaled | 8/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/10/2019 | SARAH YOUSSEF |
| Green Code | Cleared | 9/12/2019 | MICHAEL AYERS |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 10/29/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 10/29/2019 | APEKSHYA BAJRACHARYA |
| Grading Pre-Inspection | Cleared | 11/7/2019 | JENNIFER LEE |
| Specific Plan | Cleared | 11/22/2019 | OLGA RUANO |
| ZI | Cleared | 11/22/2019 | OLGA RUANO |
Contact Information
| Contractor | Ortiz L A Construction Inc; Lic. No.: 647310-B | P O BOX 4266 VALLEY VILLAGE, CA 91617 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
| Engineer | Zolfaghari,, Mohammad Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/5/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/27/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/31/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 4/15/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 4/20/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Grading Pre-Inspection | 4/20/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/20/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/30/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/13/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/13/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/13/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/13/2020 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 8/13/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/31/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/31/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 8/31/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/14/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/14/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 9/14/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/18/2020 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/18/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/18/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 9/18/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/28/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/28/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 2/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/8/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 2/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 6/15/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 6/15/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/15/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 7/15/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 7/15/2022 | Approved | HAMIK HARTOUNIAN |