8846 N FARRALONE AVE 91304
Certificate Information: 8846 N FARRALONE AVE 91304
- Application / Permit
- 19014-20000-04232
- Plan Check / Job No.
- B19VN13039
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'-6" X 35'-1" IRREGULAR SHAPE ACCESSORY DWELLING UNIT PER SB 229 AND AB 494. COMPLY WITH DEPARTMENT ORDER effective date 10/11/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2019 | ROSENDO MEDINA |
| Corrections Issued | 8/9/2019 | ROSENDO MEDINA |
| Building Plans Picked Up | 8/14/2019 | APPLICANT |
| Applicant returned to address corrections | 12/23/2019 | ROSENDO MEDINA |
| Plan Check Approved | 1/28/2020 | ROSENDO MEDINA |
| Issued | 5/27/2020 | LADBS |
| CofO in Progress | 11/21/2023 | MARK DOVICO |
| Permit Finaled | 12/29/2023 | DAVID JAMES |
| CofO Issued | 12/29/2023 | DAVID JAMES |
| Permit Finaled | 12/29/2023 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/9/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/9/2019 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/9/2019 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 10/9/2019 | MANUEL TEJADA |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2019 | JOHN LIN |
| Low Impact Development | Cleared | 10/24/2019 | MARTIN FRAGOSO |
| Sewer availability | Cleared | 10/24/2019 | JOHN LIN |
| Green Code | Cleared | 10/31/2019 | MICHAEL AYERS |
| Miscellaneous | Cleared | 11/15/2019 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 11/15/2019 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 12/11/2019 | GEORGE SUCHAND |
| GPI Written Notices | Cleared | 1/28/2020 | ROSENDO MEDINA |
| Hold | Cleared | 9/15/2020 | JASON SHEETS |
Contact Information
| Architect | Di, Zitti, Fernando; Lic. No.: C24587 | 21243 VENTURA BLVD #115 WOODLAND HILLS, CA 91364 |
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/5/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 11/5/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 12/4/2020 | Corrections Issued | MARK DOVICO |
| Footing/Foundation/Slab | 1/8/2021 | Corrections Issued | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 1/14/2021 | Conditional Approval | HAGOP BADOSSIAN |
| Deputy Drilled-In Anchors | 4/26/2021 | Conditional Approval | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 5/3/2021 | Partial Inspection | HAGOP BADOSSIAN |
| Green Building Rough | 5/3/2021 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Wood Frame | 5/3/2021 | Not Ready for Inspection | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 6/24/2021 | No Access for Inspection | HAGOP BADOSSIAN |
| PLUMBING-Rough | 6/24/2021 | No Access for Inspection | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 6/29/2021 | Corrections Issued | HAGOP BADOSSIAN |
| PLUMBING-Rough | 6/29/2021 | Corrections Issued | HAGOP BADOSSIAN |
| HVAC-Rough | 7/9/2021 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 7/9/2021 | Conditional Approval | HAGOP BADOSSIAN |
| Underground Mechanical | 7/9/2021 | Approved | HAGOP BADOSSIAN |
| HVAC-Rough | 7/15/2021 | Approved | HAGOP BADOSSIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | No Access for Inspection | HAGOP BADOSSIAN |
| Interior/Exterior Lathing | 8/19/2021 | Conditional Approval | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 12/21/2021 | Approved | ARIS ALLAHVERDIAN |
| Interior/Exterior Lathing | 12/21/2021 | Approved | ARIS ALLAHVERDIAN |
| Underground Mechanical | 12/21/2021 | Approved | ARIS ALLAHVERDIAN |
| Interior/Exterior Lathing | 2/1/2022 | Approved | ARIS ALLAHVERDIAN |
| PLUMBING-Rough | 2/1/2022 | Approved | ARIS ALLAHVERDIAN |
| Drywall Nailing | 2/9/2022 | Not Ready for Inspection | ARIS ALLAHVERDIAN |
| Insulation | 2/9/2022 | Approved | ARIS ALLAHVERDIAN |
| Drywall Nailing | 2/11/2022 | Approved | ARIS ALLAHVERDIAN |
| Green Building Rough | 2/11/2022 | Approved | ARIS ALLAHVERDIAN |
| Insulation | 6/27/2022 | No Access for Inspection | MARK DOVICO |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | ARIS ALLAHVERDIAN |
| ELECTRICAL-Final | 12/1/2022 | Approved | ARIS ALLAHVERDIAN |
| Final | 12/1/2022 | Partial Approval | ARIS ALLAHVERDIAN |
| Footing/Foundation/Slab | 12/1/2022 | Approved | ARIS ALLAHVERDIAN |
| Green Building Final | 12/1/2022 | Approved | ARIS ALLAHVERDIAN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | ARIS ALLAHVERDIAN |
| Service/Power Release | 12/1/2022 | Approved | ARIS ALLAHVERDIAN |
| Smoke Detectors | 12/1/2022 | Approved | ARIS ALLAHVERDIAN |
| Final | 4/5/2023 | Conditional Approval | MARK DOVICO |
| Final | 4/27/2023 | Corrections Issued | MARK DOVICO |
| Service/Power Release | 6/13/2023 | Approved | MARK DOVICO |