4562 N STANSBURY AVE 91423

Certificate Information: 4562 N STANSBURY AVE 91423

Application / Permit
19014-20000-04223
Plan Check / Job No.
B19VN13011
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Remove 4' x 8' portion of detached garage area, add 4' x 11' and convert to accessory dwelling unit per AB494 & SB229. All works are per WFPP
Permit Issued
Issued on 1/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2019 APPLICANT
Assigned to Plan Check Engineer 8/5/2019 ALDOUS CHIC
Corrections Issued 8/5/2019 ALDOUS CHIC
Plan Check Approved 8/14/2019 JEROME MAGAT PALMA
Issued 1/14/2020 LADBS
CofO in Progress 3/18/2021 BRENDAN LOONEY
Permit Finaled 5/15/2021 MICHAEL SMITH
CofO Issued 5/15/2021 MICHAEL SMITH
Permit Finaled 5/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/5/2019 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/6/2019 GUILLERMO PETRA
Sewer availability Cleared 8/6/2019 GUILLERMO PETRA

Contact Information

Contractor Rosegold Builders Inc; Lic. No.: 1041947-B 12200 RIVERSIDE DRIVE UNIT 4      VALLEY VILLAGE, CA 91607

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/19/2020 Corrections Issued CHARLES POWELL
PLUMBING-Rough 2/19/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 3/27/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 4/2/2020 Conditional Approval DANIEL ORRANTE
BUILDING-Rough-Frame 6/12/2020 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Approved CHARLES POWELL
Green Building Rough 6/12/2020 Not Ready for Inspection CHARLES POWELL
MERV13>=Rough 6/12/2020 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 7/30/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 7/30/2020 Approved CHARLES POWELL
Green Building Rough 7/30/2020 Approved CHARLES POWELL
MERV13>=Rough 7/30/2020 Approved CHARLES POWELL
PLUMBING-Rough 7/30/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 9/3/2020 Approved CHARLES POWELL
Drywall Nailing 9/16/2020 Approved BRENDAN LOONEY
ELECTRICAL-Final 2/24/2021 Corrections Issued ARAM AVEDISIAN
Final 2/24/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 2/24/2021 Approved ARAM AVEDISIAN
Green Building Final 2/24/2021 Approved ARAM AVEDISIAN
MERV13>=Final 2/24/2021 Approved ARAM AVEDISIAN
PLUMBING-Final 2/24/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 2/24/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/1/2021 Approved BRENDAN LOONEY
Final 3/1/2021 Not Ready for Inspection BRENDAN LOONEY
Final 3/17/2021 OK to Issue CofO BRENDAN LOONEY