4562 N STANSBURY AVE 91423
Certificate Information: 4562 N STANSBURY AVE 91423
- Application / Permit
- 19014-20000-04223
- Plan Check / Job No.
- B19VN13011
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Remove 4' x 8' portion of detached garage area, add 4' x 11' and convert to accessory dwelling unit per AB494 & SB229. All works are per WFPP
- Permit Issued
- Issued on 1/14/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2019 | ALDOUS CHIC |
| Corrections Issued | 8/5/2019 | ALDOUS CHIC |
| Plan Check Approved | 8/14/2019 | JEROME MAGAT PALMA |
| Issued | 1/14/2020 | LADBS |
| CofO in Progress | 3/18/2021 | BRENDAN LOONEY |
| Permit Finaled | 5/15/2021 | MICHAEL SMITH |
| CofO Issued | 5/15/2021 | MICHAEL SMITH |
| Permit Finaled | 5/15/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2019 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/6/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Rosegold Builders Inc; Lic. No.: 1041947-B | 12200 RIVERSIDE DRIVE UNIT 4 VALLEY VILLAGE, CA 91607 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/19/2020 | Corrections Issued | CHARLES POWELL |
| PLUMBING-Rough | 2/19/2020 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 3/27/2020 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 4/2/2020 | Conditional Approval | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 6/12/2020 | Not Ready for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 6/12/2020 | Not Ready for Inspection | CHARLES POWELL |
| MERV13>=Rough | 6/12/2020 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 7/30/2020 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 7/30/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 7/30/2020 | Approved | CHARLES POWELL |
| MERV13>=Rough | 7/30/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 7/30/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 9/3/2020 | Approved | CHARLES POWELL |
| Drywall Nailing | 9/16/2020 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 2/24/2021 | Corrections Issued | ARAM AVEDISIAN |
| Final | 2/24/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/24/2021 | Approved | ARAM AVEDISIAN |
| Green Building Final | 2/24/2021 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 2/24/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 2/24/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 2/24/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/1/2021 | Approved | BRENDAN LOONEY |
| Final | 3/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 3/17/2021 | OK to Issue CofO | BRENDAN LOONEY |