9453 N BEACHY AVE 91331
Certificate Information: 9453 N BEACHY AVE 91331
- Application / Permit
- 19014-20000-04213
- Plan Check / Job No.
- B19VN12982
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE (E) 3'-0" X 14'-0" PORTION AND REMOVE 20'-0" X 4'-0" PORTION OF (E) DETACHED GARAGE. 25'-0" X 21'-10" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2019 | JENNIFER LEE |
| Corrections Issued | 8/13/2019 | JENNIFER LEE |
| Plan Check Approved | 1/28/2020 | JEROME MAGAT PALMA |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 11/12/2020 | DANIEL ORRANTE |
| Permit Finaled | 1/15/2021 | DANIEL ORRANTE |
| CofO Issued | 1/15/2021 | DANIEL ORRANTE |
| Permit Finaled | 1/15/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/11/2019 | RIDWAN HARDY |
| Address approval | Cleared | 12/13/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2020 | ELAINE LEI |
| Low Impact Development | Cleared | 1/23/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 1/23/2020 | ELAINE LEI |
| Sewer availability | Cleared | 1/23/2020 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 3/5/2020 | Partial Inspection | WILLIAM KUEHN |
| Sewer | 3/5/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 5/13/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 5/13/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 5/13/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/13/2020 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/15/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2020 | Partial Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 5/15/2020 | Approved | WILLIAM KUEHN |
| Insulation | 5/26/2020 | Approved | MATTHEW NELSON |
| Insulation | 5/26/2020 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 5/26/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/5/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 6/5/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 6/5/2020 | Partial Inspection | WILLIAM KUEHN |
| Shower Pan | 6/5/2020 | Approved | WILLIAM KUEHN |
| Gas Test | 8/17/2020 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/29/2020 | SGSOV Not Ready | GREGG CUMMINGS |
| Final | 9/30/2020 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Final | 9/30/2020 | No Access for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 9/30/2020 | No Access for Inspection | GREGG CUMMINGS |
| Final | 10/1/2020 | Corrections Issued | DANIEL ORRANTE |
| Green Building Final | 10/1/2020 | Approved | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 10/1/2020 | SGSOV Approved | DANIEL ORRANTE |
| Smoke Detectors | 10/1/2020 | Approved | DANIEL ORRANTE |
| Final | 10/21/2020 | Corrections Issued | DANIEL ORRANTE |
| Final | 11/9/2020 | OK to Issue CofO | DANIEL ORRANTE |