7898 W WILLOW GLEN ROAD 90046

Certificate Information: 7898 W WILLOW GLEN ROAD 90046

Application / Permit
19014-20000-04166
Plan Check / Job No.
B19VN12844
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENLCOSE (E) CARPORT AT FRONT TO RELOCATE (E) KITCHEN AND FOR NEW LAUNDRY ROOM. CONVERT PORTION OF (E) CRAWL SPACE FOR NEW BEDROOM AND BATHROOM. COMPLY WITH DEPARTMENT ORDER effective date 09/13/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
Permit Issued
Issued on 1/27/2020
Issuing Office
Valley
Current Status
Issued on 1/27/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2019 APPLICANT
Assigned to Plan Check Engineer 8/29/2019 ROSENDO MEDINA
Corrections Issued 9/11/2019 ROSENDO MEDINA
Quality Review Completed 9/13/2019 OMID HEDAYAT
Building Plans Picked Up 10/4/2019 APPLICANT
Green Plans Picked Up 10/4/2019 APPLICANT
Plan Check Approved 1/27/2020 ROSENDO MEDINA
Issued 1/27/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/16/2019 JEANIE LAM
Sewer availability Cleared 10/16/2019 JEANIE LAM
ZA Case Cleared 10/16/2019 RICHARD REASER
Hydrant and Access approval Cleared 10/21/2019 JOHN CONNEALLY
Miscellaneous Cleared 10/22/2019 LIZZI BEDUYA
Specific Plan Cleared 10/22/2019 LIZZI BEDUYA
Green Code Cleared 11/19/2019 DAVID MATSON
Grading Pre-Inspection Cleared 1/27/2020 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/11/2021 Approved JOHN TCHANG
Pre-Inspection 2/2/2023 Corrections Issued PATRICK LIEBREGT
BUILDING-Rough-Frame 3/24/2025 Not Ready for Inspection JOEL ORDAZ
Green Building Rough 3/24/2025 Not Ready for Inspection JOEL ORDAZ
Deputy Drilled-In Anchors 4/1/2025 Approved JOEL ORDAZ
ELECTRICAL-Rough 4/4/2025 Not Ready for Inspection JOEL ORDAZ
Excavation/Setback/Form/Re-Bar 4/4/2025 Approved JOEL ORDAZ
HVAC-Rough 4/4/2025 Not Ready for Inspection JOEL ORDAZ
PLUMBING-Rough 4/4/2025 Not Ready for Inspection JOEL ORDAZ
Wood Frame 4/4/2025 Not Ready for Inspection JOEL ORDAZ
ELECTRICAL-Rough 4/9/2025 Corrections Issued JOEL ORDAZ
HVAC-Rough 4/9/2025 Approved JOEL ORDAZ
PLUMBING-Rough 4/9/2025 Corrections Issued JOEL ORDAZ
Insulation 4/30/2025 Approved JOEL ORDAZ
Rough-Elec/Plmb/HVAC 4/30/2025 Approved JOEL ORDAZ
Shower Pan 4/30/2025 Approved JOEL ORDAZ
Drywall Nailing 5/6/2025 Approved JOEL ORDAZ
Green Building Rough 5/6/2025 Approved JOEL ORDAZ
Interior/Exterior Lathing 5/6/2025 Approved JOEL ORDAZ
Shower Pan 10/31/2025 Approved JOEL ORDAZ
Interior/Exterior Lathing 12/22/2025 Approved JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 6/10/2026 SGSOV Not Ready JOEL ORDAZ
Pre-Inspection 6/17/2026 Corrections Issued JOEL ORDAZ
BUILDING-Rough-Frame 6/24/2026 Approved JOEL ORDAZ
Final 6/24/2026 Partial Approval JOEL ORDAZ
Footing/Foundation/Slab 6/24/2026 Approved JOEL ORDAZ
Green Building Final 6/24/2026 Approved JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 6/24/2026 SGSOV Approved JOEL ORDAZ
Smoke Detectors 6/24/2026 Approved JOEL ORDAZ