5415 N AMESTOY AVE 91316
Certificate Information: 5415 N AMESTOY AVE 91316
- Application / Permit
- 19014-20000-04156
- Plan Check / Job No.
- B19VN12791
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE ALTERATION AND REMODEL OF (E) SFD, REMOVE 78.2SF PORTION OF EXISTING, REFRAME ROOF AT 418 SF OF EXISTING LIVING ROOM AREA AND ADD TWO TRELLIS AT 610SF TOTAL [SEE COMMENTS].
- Permit Issued
- Issued on 10/15/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2019 | APPLICANT |
| Green Plans Picked Up | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | DAWN MC NULTY |
| Corrections Issued | 8/20/2019 | DAWN MC NULTY |
| Quality Review Completed | 8/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 8/22/2019 | APPLICANT |
| Applicant returned to address corrections | 9/10/2019 | DAWN MC NULTY |
| Applicant returned to address corrections | 9/13/2019 | DAWN MC NULTY |
| Applicant returned to address corrections | 9/24/2019 | DAWN MC NULTY |
| Applicant returned to address corrections | 10/7/2019 | DAWN MC NULTY |
| Applicant returned to address corrections | 10/9/2019 | DAWN MC NULTY |
| Plan Check Approved | 10/15/2019 | DAWN MC NULTY |
| Issued | 10/15/2019 | LADBS |
| CofO in Progress | 9/27/2021 | STEVEN BACK |
| CofO Issued | 12/22/2021 | MICHAEL SMITH |
| Permit Finaled | 12/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2019 | JULIUS GARCIA |
| Miscellaneous | Cleared | 8/28/2019 | DAISY BENICIA |
| Permit | Cleared | 8/29/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 8/30/2019 | JEANETTE VONG |
| Green Code | Cleared | 9/12/2019 | AARON COSTA |
| Low Impact Development | Cleared | 10/11/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 10/11/2019 | JEANETTE VONG |
Contact Information
| Contractor | Imperial Enterprises Investments & Development; Lic. No.: 793784-B | 17200 VENTURA BLVD STE 301 ENCINO, CA 91316 |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/7/2019 | Not Ready for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 12/19/2019 | Corrections Issued | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 12/20/2019 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2020 | Partial Approval | STEVEN BACK |
| Wood Frame | 1/24/2020 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 3/17/2020 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 3/17/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 3/17/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 3/18/2020 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 5/29/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 5/29/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Partial Approval | STEVEN BACK |
| Green Building Rough | 5/29/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 5/29/2020 | Not Ready for Inspection | STEVEN BACK |
| MERV13>=Rough | 5/29/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/29/2020 | Approved | STEVEN BACK |
| Sewer | 5/29/2020 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 6/12/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 6/12/2020 | Approved | STEVEN BACK |
| Special/Order Compliance | 7/20/2020 | Corrections Issued | STEVEN BACK |
| Shower Pan | 8/4/2020 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 8/27/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 8/27/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/27/2020 | Approved | STEVEN BACK |
| Shower Pan | 8/27/2020 | Approved | STEVEN BACK |
| Insulation | 9/2/2020 | Corrections Issued | STEVEN BACK |
| Insulation | 9/10/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 10/14/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 5/24/2021 | Partial Approval | RONALD COWAN |
| HVAC-Final | 5/24/2021 | Approved | RONALD COWAN |
| PLUMBING-Final | 5/24/2021 | Not Ready for Inspection | RONALD COWAN |
| ELECTRICAL-Final | 6/8/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 6/8/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 6/8/2021 | Approved | STEVEN BACK |
| Green Building Final | 6/8/2021 | Not Ready for Inspection | STEVEN BACK |
| MERV13>=Final | 6/8/2021 | Approved | STEVEN BACK |
| PLUMBING-Final | 6/8/2021 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 6/8/2021 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 6/17/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Final | 6/17/2021 | Approved | STEVEN BACK |
| Service/Power Release | 6/17/2021 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 6/25/2021 | Not Ready for Inspection | STEVEN BACK |
| Service/Power Release | 6/25/2021 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Not Ready | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/17/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 8/17/2021 | Approved | STEVEN BACK |
| Final | 9/27/2021 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 9/27/2021 | Approved | STEVEN BACK |
| Service/Power Release | 9/27/2021 | Approved | STEVEN BACK |