11028 W CALIFA ST 91601
Certificate Information: 11028 W CALIFA ST 91601
- Application / Permit
- 19014-20000-04103
- Plan Check / Job No.
- B19VN12645
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Remove all on grade structure of detached garage except slab and 18' (L) East side wall with footing, rebuild with irregular shape 37'4" x 29'3" addition for new accessory dwelling unit and attached patio cover per AB494 & SB229. All works are per design
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2019 | ALDOUS CHIC |
| Corrections Issued | 7/30/2019 | ALDOUS CHIC |
| Plan Check Approved | 9/24/2019 | ALDOUS CHIC |
| Issued | 9/3/2020 | APPLICANT |
| CofO in Progress | 3/4/2021 | DANIEL DREW |
| CofO Issued | 7/17/2021 | MICHAEL SMITH |
| Permit Finaled | 7/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2019 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 7/30/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2019 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/3/2019 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 9/24/2019 | ANDRES COVARRUBIAS |
Contact Information
| Contractor | Armscraft Construction Inc; Lic. No.: 905702-B | 1125 E BROADWAY #15 GLENDALE, CA 91205 |
| Engineer | , ; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2020 | Approved | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | Partial Approval | DANIEL DREW |
| PLUMBING-Rough | 10/9/2020 | Partial Approval | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 10/19/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/19/2020 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/22/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 11/30/2020 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2020 | Partial Approval | DAVID MATSON |
| PLUMBING-Rough | 11/30/2020 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 12/1/2020 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 12/1/2020 | Approved | THOMAS FINNILA |
| Sewer | 12/1/2020 | Corrections Issued | THOMAS FINNILA |
| Sewer | 12/7/2020 | Approved | DANIEL DREW |
| Shower Pan | 12/7/2020 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 12/10/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 12/11/2020 | Approved | DANIEL DREW |
| Green Building Rough | 12/11/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 12/11/2020 | Not Ready for Inspection | DANIEL DREW |
| Insulation | 12/16/2020 | Conditional Approval | DANIEL DREW |
| Insulation | 12/21/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 12/21/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 12/24/2020 | Approved | DANIEL DREW |
| Service/Power Release | 1/26/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Final | 2/4/2021 | Approved | DANIEL DREW |
| HVAC-Final | 2/4/2021 | Corrections Issued | DANIEL DREW |
| PLUMBING-Final | 2/4/2021 | Approved | DANIEL DREW |
| HVAC-Final | 2/16/2021 | Approved | DANIEL DREW |
| Service/Power Release | 2/16/2021 | Not Ready for Inspection | DANIEL DREW |
| Footing/Foundation/Slab | 3/3/2021 | Approved | DANIEL DREW |
| Green Building Final | 3/3/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 3/3/2021 | SGSOV Not Ready | DANIEL DREW |
| Smoke Detectors | 3/3/2021 | Approved | DANIEL DREW |
| Final | 3/4/2021 | OK to Issue CofO | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Approved | DANIEL DREW |
| Service/Power Release | 3/4/2021 | Approved | DANIEL DREW |