11551 W OTSEGO ST 91601
Certificate Information: 11551 W OTSEGO ST 91601
- Application / Permit
- 19014-20000-04101
- Plan Check / Job No.
- B19VN12634
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 16'-6" 13'-6" ADDITION TO & CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 7/31/2019 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/31/2019 | APPLICANT |
| Plan Check Approved | 9/6/2019 | JEROME MAGAT PALMA |
| Issued | 1/27/2020 | LADBS |
| CofO in Progress | 5/25/2021 | JOHN HAYES |
| Permit Finaled | 8/21/2021 | MICHAEL SMITH |
| CofO Issued | 8/21/2021 | MICHAEL SMITH |
| Permit Finaled | 8/21/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 8/6/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/6/2019 | GUILLERMO PETRA |
| ZI | Cleared | 8/19/2019 | MARIANNE KING |
| Low Impact Development | Cleared | 9/5/2019 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Architect | Reynolds,, Eve Carole; Lic. No.: C25225 | 3027 WINDSOR AVENUE LOS ANGELES, CA 90039 |
| Contractor | Bestall Construction Inc; Lic. No.: 953477-B | 2532 EDWARDS AVENUE # 6 SOUTH EL MONTE, CA 91733 |
| Engineer | Downey,, Henry Ross; Lic. No.: S2628 | 7463 VARNA AVE NORTH HOLLYWOOD, CA 916054011 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/11/2020 | Corrections Issued | JEFFREY PARD |
| Footing/Foundation/Slab | 3/26/2020 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/8/2020 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 5/8/2020 | Not Ready for Inspection | JEFFREY PARD |
| MERV13>=Rough | 5/8/2020 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 6/26/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/26/2020 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/8/2020 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 7/8/2020 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 7/8/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 7/8/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/16/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 7/16/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/21/2020 | Corrections Issued | THOMAS FINNILA |
| Wood Frame | 7/21/2020 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/30/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/30/2020 | Approved | THOMAS FINNILA |
| Green Building Rough | 7/30/2020 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 7/30/2020 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 7/30/2020 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Approved | THOMAS FINNILA |
| Insulation | 8/11/2020 | Corrections Issued | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 8/11/2020 | Approved | THOMAS FINNILA |
| Gas Test | 9/4/2020 | Approved | THOMAS FINNILA |
| Insulation | 9/4/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/4/2020 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 9/25/2020 | Approved | THOMAS FINNILA |
| Shower Pan | 10/2/2020 | Approved | THOMAS FINNILA |
| Final | 12/29/2020 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Not Ready | BEAU COLLINS |
| Shower Pan | 12/29/2020 | Approved | BEAU COLLINS |
| ELECTRICAL-Final | 1/12/2021 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 1/12/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 1/12/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 1/12/2021 | Approved | THOMAS FINNILA |
| Final | 3/12/2021 | No Access for Inspection | THOMAS FINNILA |
| Green Building Final | 3/12/2021 | No Access for Inspection | THOMAS FINNILA |
| MERV13>=Final | 3/12/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 3/12/2021 | No Access for Inspection | THOMAS FINNILA |
| Final | 3/18/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 3/18/2021 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 3/18/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 4/5/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/5/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/5/2021 | Not Ready for Inspection | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Final | 4/26/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 4/26/2021 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/26/2021 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 5/25/2021 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 5/25/2021 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/25/2021 | SGSOV Approved | JOHN HAYES |