5657 N SALOMA AVE 91411

Certificate Information: 5657 N SALOMA AVE 91411

Application / Permit
19014-20000-04090
Plan Check / Job No.
B19VN12588
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
40'-0" X 26'-7" IRREGULAR FIRST FLOOR ADDITION AT REAR & 18'-4" X 9'-5" IRREGULAR ADDITION AT FRONT TO (E) SINGLE FAMILY DWELLING. NEW 22'-0" X 9'-0" COVERED PATIO AT REAR. REMODEL BEDROOMS, BATHROOMS, AND KITCHEN. COMPLY WITH DEPARTMENT ORDER effective date 07/09/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
Permit Issued
Issued on 8/20/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2019 APPLICANT
Assigned to Plan Check Engineer 7/30/2019 ROSENDO MEDINA
Corrections Issued 7/31/2019 ROSENDO MEDINA
Plan Check Approved 8/20/2019 ROSENDO MEDINA
Issued 8/20/2019 LADBS
Building Plans Picked Up 4/20/2021 APPLICANT
CofO in Progress 12/27/2021 MICHAEL TEMPLE
Permit Finaled 1/3/2022 MICHAEL SMITH
CofO Issued 1/3/2022 MICHAEL SMITH
Permit Finaled 1/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/8/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 8/8/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 8/12/2019 GEORGE SUCHAND
Low Impact Development Cleared 8/12/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/12/2019 GABRIEL ROBLES

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/1/2019 Approved ARAM AVEDISIAN
Deputy Drilled-In Anchors 10/11/2019 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 10/15/2019 Partial Approval ARAM AVEDISIAN
Green Building Rough 10/15/2019 Not Ready for Inspection ARAM AVEDISIAN
Gas Test 10/21/2019 Partial Inspection ROBERT MINASSIANS
PLUMBING-Rough 10/21/2019 Partial Inspection ROBERT MINASSIANS
PLUMBING-Rough 11/1/2019 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/13/2019 No Access for Inspection ARAM AVEDISIAN
Green Building Rough 12/13/2019 No Access for Inspection ARAM AVEDISIAN
Special/Order Compliance 1/23/2020 Approved ARAM AVEDISIAN
Special/Order Compliance 1/28/2020 Approved MISAEL ESPARZA
Special/Order Compliance 5/12/2020 Partial Inspection MISAEL ESPARZA
Special/Order Compliance 9/1/2020 No Access for Inspection MICHAEL TEMPLE
Special/Order Compliance 9/4/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 12/31/2020 Corrections Issued ARTHUR SARGSYAN
Green Building Rough 12/31/2020 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/14/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 4/14/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 4/14/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 4/22/2021 Corrections Issued ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2021 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Rough 4/22/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 4/22/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Partial Approval DAVID SCANTLIN
Gas Test 5/10/2021 Approved MICHAEL TEMPLE
PLUMBING-Rough 5/10/2021 Approved MICHAEL TEMPLE
HVAC-Rough 5/14/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 5/14/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/18/2021 Approved MARK JOHNSON
Service/Power Release 5/18/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 5/21/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 5/21/2021 Not Ready for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 7/15/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Approved ARTHUR SARGSYAN
Green Building Rough 7/15/2021 Approved ARTHUR SARGSYAN
Insulation 7/27/2021 Approved AMY COLIN
Interior/Exterior Lathing 7/27/2021 Not Ready for Inspection AMY COLIN
Insulation 7/28/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 7/28/2021 Partial Approval ALAN MORELOS
Special/Order Compliance 8/20/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/7/2021 Partial Approval AMY COLIN
Shower Pan 9/7/2021 Corrections Issued AMY COLIN
Interior/Exterior Lathing 9/8/2021 Approved AMY COLIN
Shower Pan 9/8/2021 Approved AMY COLIN
Interior/Exterior Lathing 9/10/2021 Partial Inspection MISAEL ESPARZA
Shower Pan 9/10/2021 Partial Inspection MISAEL ESPARZA
Service/Power Release 9/22/2021 Not Ready for Inspection RICHARD DOCKUS
Service/Power Release 9/23/2021 Approved MICHAEL TEMPLE
Drywall Nailing 11/3/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 11/3/2021 Not Ready for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV Not Ready RICHARD DOCKUS
Smoke Detectors 11/3/2021 Not Ready for Inspection RICHARD DOCKUS
Final 11/5/2021 Not Ready for Inspection RICHARD DOCKUS
Final 11/9/2021 Corrections Issued RICHARD DOCKUS
Drywall Nailing 11/12/2021 Approved RICHARD DOCKUS
Final 11/12/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 11/12/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/12/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 11/12/2021 Approved RICHARD DOCKUS
Final 12/10/2021 Not Ready for Inspection RICHARD DOCKUS
Final 12/27/2021 OK to Issue CofO MICHAEL TEMPLE