15114 W BRAND BLVD 91345
Certificate Information: 15114 W BRAND BLVD 91345
- Application / Permit
- 19014-20000-04084
- Plan Check / Job No.
- B19VN12569
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ADDITION OF A 15' x 20' REC. ROOM TO (E) DET. GARAGE. WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/23/2019
- Issuing Office
- Valley
- Current Status
- Issued on 12/23/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2019 | ANGELICA DAVE |
| Corrections Issued | 7/29/2019 | ANGELICA DAVE |
| Plan Check Approved | 12/23/2019 | SARKIS HARABEDIAN |
| Issued | 12/23/2019 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 7/29/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/8/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/8/2020 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/15/2020 | Approved | BEAU COLLINS |
| Pre-Inspection | 6/5/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 6/5/2020 | Approved | PIERRE VEGA |
| BUILDING-Rough-Frame | 8/12/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Drywall Nailing | 8/12/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 8/12/2020 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 8/12/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Rough | 8/12/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 8/12/2020 | SGSOV Not Ready | MICHAEL TEMPLE |
| Smoke Detectors | 8/12/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 7/26/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 7/26/2021 | Partial Approval | JENNIFER RABUCHIN |
| Final | 7/26/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/26/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 7/26/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/26/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/26/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/30/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/30/2021 | Approved | JENNIFER RABUCHIN |
| Final | 7/30/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 7/30/2021 | Approved | JENNIFER RABUCHIN |