7708 N WISH AVE 91406

Certificate Information: 7708 N WISH AVE 91406

Application / Permit
19014-20000-04083
Plan Check / Job No.
B19VN12568
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 15'10" x 16' TO DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 8/7/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2019 APPLICANT
Assigned to Plan Check Engineer 7/29/2019 ALDOUS CHIC
Corrections Issued 7/29/2019 ALDOUS CHIC
Plan Check Approved 7/30/2019 GUANG MIN TUNG
Issued 8/7/2019 LADBS
CofO in Progress 2/15/2022 MICHAEL TEMPLE
Permit Finaled 2/17/2022 MICHAEL SMITH
CofO Issued 2/17/2022 MICHAEL SMITH
Permit Finaled 2/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/29/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 7/29/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 7/29/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 7/29/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/28/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 4/28/2020 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 5/1/2020 Approved JEFFREY PARD
PLUMBING-Rough 5/1/2020 Partial Approval JEFFREY PARD
Gas Test 5/5/2020 Approved GREGG CUMMINGS
Sewer 5/20/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 6/29/2020 Corrections Issued DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 6/29/2020 Approved DANIEL DREW
Gas Test 6/29/2020 Approved DANIEL DREW
PLUMBING-Rough 6/29/2020 Approved DANIEL DREW
Pre-Inspection 7/22/2020 Partial Inspection MICHAEL TEMPLE
Pre-Inspection 7/23/2020 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 8/20/2020 Approved DANIEL DREW
HVAC-Rough 8/20/2020 Approved DANIEL DREW
Underground Mechanical 10/15/2020 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 12/4/2020 Corrections Issued MICHAEL TEMPLE
Drywall Nailing 12/4/2020 Not Ready for Inspection MICHAEL TEMPLE
Green Building Rough 12/4/2020 Not Ready for Inspection MICHAEL TEMPLE
Interior/Exterior Lathing 12/4/2020 Not Ready for Inspection MICHAEL TEMPLE
Drywall Nailing 12/18/2020 Approved ARTHUR SARGSYAN
Green Building Rough 12/18/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 12/18/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 1/4/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/12/2021 Approved ARTHUR SARGSYAN
Final 3/12/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 3/12/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 3/12/2021 Approved ARTHUR SARGSYAN
Final 2/15/2022 OK to Issue CofO MICHAEL TEMPLE